Funding source: city of Chandler 2 Cooper Road improvement

Lindsay Road and Gilbert Road. Status: Traffic restrictions on Lindsay be- gan in March and will remain throughout the remainder of the project. The project is coordinating traffic control with the Germann Road improvements project. Timeline: October 2020-November 2021 Cost: $18.15 million Funding sources: town of Gilbert bonds and funds, Maricopa Association of Gov- ernments, developer contributions 4 Val Vista Drive widening The town widened Val Vista Drive from Appleby Road to Riggs Road. Traffic sig- nals were installed at Appleby, Ocotillo and Chandler Heights roads. Status: Traffic signals were energized Aug. 27. Permanent striping will be laid down by Oct. 8. Timeline: March 2020-October 2021 Cost: $25.96 million Funding sources: town of Gilbert, Maricopa Association of Governments funds

W. ELLIOT RD.

An effort is underway to expand Cooper Road to four lanes—two lanes in each di- rection. The project begins about 3,500 feet north of Chandler Heights Road to Riggs Road. Improvements include the construction of raised medians, bike lanes, left-turn lanes, sidewalks and traffic signals. Status: Crews have completed instal- lation of a water line on Cooper from Blue Ridge Way to Chandler Heights and are conducting pipeline testing over the next week or two to put the newly installed line into service. Residents will be notified in advance of any planned disruption to water service. Grading crews are working to grade for block wall foundations on the west side of Cooper from Victoria to Chandler Heights, and as the foundation work moves north, block wall installation will follow, which began the week of Aug. 9. Timeline: February 2020-September 2022 Cost: $17.17 million Funding source: city of Chandler 3 Lindsay Road/Loop 202 interchange An interchange at Lindsay Road and Loop 202 will be built to provide access to Loop 202 and a frontage road system on the north side of Loop 202 between

101

87

W. WARNER RD.

1

W. RAY RD.

W. CHANDLER BLVD.

W. PECOS RD.

202

W. GERMANN RD.

3

E. APPLEBY RD.

10

4

2

N

MAP NOT TO SCALE

ONGOING PROJECTS 1 Milling and paving on Ray Road The work on Ray Road is part of an an- nual effort to patch asphalt on Chandler streets. The work is being done on Ray in small sections, allowing crews to work on a small section for a day or two at a time and then move on, according to the city.

Status: Patching work is happening on small segments on Ray throughout September. Construction work is largely taking place between Kyrene Road and Price Road. Lane disruptions are expect- ed along Ray Road for the duration of the project.

ALL INFORMATION ON THIS PAGE WAS UP TO DATE AS OF SEPT. 14. NEWS OR QUESTIONS ABOUT THESE OR OTHER LOCAL TRANSPORTATION PROJECTS? EMAIL US AT CHNNEWS@COMMUNITYIMPACT.COM.

Timeline: Aug. 1-Sept. 29 Cost: Cost not available

RATES DIP TOWARDS 3 YEAR LOWS

Don’t Miss Your Opportunity to Refinance and Lower your Payment

Local Chandler Lender - #1 Retail Lender in Arizona Cash Out, Rate and Term, and Purchase Available 100% Financing/$0 Money Down Loans Available Low Rates Speed Service Experience Trust

KIMBERLY COSMAN Loan Officer

Call Now

(480) 316-5134 NMLS# 1064431

Copyright 2021 Fairway Independent Mortgage Corporation. NMLS #2289. 4750 S Biltmore Lane. Madison, WI 53718. 1-866-912-4800. All rights reserved. This is not an offer to enter into an agreement. Not all customers will qualify. Information, rates and programs are subject to change without notice. All products are subject to credit and property approval. Other restriction and limitations may apply. Equal Housing Lender. AZ License #BK-0904162

55 N Arizona Place, Suite 103 Chandler, AZ 85225 kimberly.cosman@fairwaymc.com

6

COMMUNITY IMPACT NEWSPAPER • COMMUNITYIMPACT.COM

Powered by