Spring - Klein Edition | June 2026

BY JESSICA SHORTEN

• Funding source: Harris County Precinct 3 6 Spring Stuebner Road expansion

this project will construct a four-lane boulevard from Bavaria Drive to Cossey Road with a raised median. Update: An engineering study of the roadway began in January. • Timeline: Jan. 2026-Dec. 2026 • Cost: $4.3 million • Funding source: Harris County Precinct 3

Ongoing project

Project: This project will expand Spring Stuebner Road from two to four lanes from west of Leitner Lane to the Grand Parkway. Existing drainage and traffic signals will also be improved and added as needed. Update: Precinct 3 officials said construction is wrapping up on the project. • Timeline: Second quarter 2026 • Cost: $8.1 million • Funding source: Harris County Precinct 3

Ongoing projects

4 Hargrave Road asphalt rehabilitation Project: This project will allow for asphalt rehabilitation on Hargrave Road from Hwy. 249 to Falba Road. Update: The surveying and testing of materials for the

Completed projects

project was completed in April. • Timeline: April-September 2026 • Cost: $2.5 million

7 Spring Cypress Road and Louetta Road asphalt rehabilitation Project: This project will rehabilitate asphalt on Spring Cypress Road, from A west of Stuebner Airline to east of T.C. Jester Blvd. and B Louetta Road, from Old Louetta to east of Champion Forest Drive. Update: Precinct 3 officials completed the rehabilitation of asphalt along both roadways in late May. • Timeline: Jan. 2026-May 2026 • Cost: $6.5 million • Funding source: Harris County Precinct 3

8 Louetta Road asphalt rehabilitation Project: This project will allow for the asphalt rehabilitation of Louetta Road from Champion Forest Drive to Holzwarth Road. Update: Asphalt work is nearly complete and striping is underway. • Timeline: February-June 2026 • Cost: $539,909 • Funding source: Harris County Precinct 3

• Funding source: Harris County Precinct 3 5 Stuebner Airline bridge repairs Project: This project will repair the bridge portion of Stuebner Airline Road over Cypress Creek near Cypresswood Drive. Update: Work has begun on the bridge repair along Stuebner Airline. • Timeline: December 2025-April 2026 • Cost: $900,000

Ches to Savings! ®

SPRING STUEBNER 6603 Spring Stuebner Rd (281) 288-0239

NORTH LOUETTA 1614 Louetta (281) 350-1198

WILLOWBROOK 6927 FM 1960 W (281) 580-1734

LOUETTA 7314 Louetta (281) 370-1986

KUYKENDAHL 13313 Kuykendahl (281) 873-5220

Powered by