NEM 10 2025

BY THOMAS LEFFLER

Measuring the impact

Looking ahead

The timing of the project is based on the expected traffic growth along I-35. According to TxDOT, traffic volume along I-35 is expected to increase by 40% to 130% in daily traffic from the preconstruction to post-construction period. Despite the growth, travel time from FM 3009 to the Frost Bank Center is expected to decline by 41% to 48% once construction is complete.

The project will also contribute to the already rapid business growth in the area. Scott Wayman, executive director of the Schertz Economic Development Corporation, said the city has been transitioning to retail operations off the interstate. “[I-35] is a tremendous generator for any city, [but] especially between San Antonio and New Braunfels right now,” Wayman said.

The project—now 62% complete—is estimated to wrap up in late 2027, Galindo said. Residents can stay informed about road closures that affect them through TxDOT’s social media channels.

2019

August 2019: public hearing held on project

2020 2021 2022 2023 2024 2025 2026

I-35 NEX Central daily traffic

June 2022: construction begins October 2022: first drill shaft complete January 2023: first bridge column complete June 2023: first bridge bent caps complete January 2025: first 1,000 bridge beams complete

Preconstruction

Main lanes when complete

Elevated lanes when complete

Fall 2027: construction complete

2027

Salado Creek

FM 1518

Walzem Road

Thousand Oaks Drive

17