Transportation
FM 1488 median project underway
What they’re saying
Leo Flores said. The medians are set to vary in width from 1 foot to 14 feet. The project, which has been in the works since 2019, aims to reduce crashes, improve mobility, and support existing and future development, Flores said. It is anticipated to cost $10.23 million, according to TxDOT.
As of Dec. 1, work on a project to install raised medians on FM 1488 from I-45 to Mostyn Drive was 26% complete, according to the Texas Department of Transportation. While construction has yet to begin on the raised medians, TxDOT is currently working on truck loons, which add pavement to help trucks make U-turns, Public Information Officer
“I just went through this process on [Hwy.] 105, and it was a mess. ... I do believe it’s going to be a hassle—I do believe people are going to drive up the road and go somewhere else, so I’m not a fan of [the median].” MIKE KELTON, OWNER OF TREEHOUSE CAFE ON FM 1488 AND HUNGER CRUSH CAFE ON HWY. 105
Timeline: completion in fourth quarter of 2025
Funding sources: federal, state
MOSTYN DR.
“You may have to go down and then make a turn and come back around, but ... I would easily trade inconvenience for safety;
45
1488
KUYKENDAHL RD.
249
242
The Woodlands
149
2978
that is not even an issue.” JEANINE WEBER, RESIDENT OF WOODLAND LANDINGS
GOSLING RD.
N
SOURCE: TEXAS DEPARTMENT OF TRANSPORTATION/COMMUNITY IMPACT