Sugar Land begins $1.9M design for Public Safety Training Facility Phase 3

More improvements are coming to Sugar Land’s Public Safety Training Facility. At a March 17 meeting, Sugar Land City Council approved a nearly $1.9 million design contract with Martinez Architects LP for the third phase of the city’s Public Safety Training Facility. The project aims to transition the police and re departments from training facilities in other communities to Sugar Land, said Lane Wolf, senior manager of vertical construction for Sugar Land. The third phase will be funded by the city’s $350 million general obligation bond approved by voters in November 2024, Community Impact reported. The bond allocated $30 million for the project. “It’s great that the city of Sugar Land is seen as a regional leader in police, re, [Emergency Medical Services] emergency training and preparedness,” council member Robert Boettcher said. “The continued investment in it is a great way to continue that.” The city rst purchased the Central Prison Unit property in 2016 followed by site demolition and asbestos

Public Safety Training Facility phases Phase 1 Completed

Phase 2 Interim gun range Conex re prop Phase 2

Completed

P

New Homes from the $300s in Rosenberg at Brookewater An 850-acre community with parks, trails, and room to grow— just outside Sugar Land. • Well-designed homes from the $300s • 200+ acres of trails, parks, lakes, and open space • Resort-style amenities coming soon

Apparatus bays A romper room Simulation training space Classrooms Parking

Phase 3

Ongoing

50-yard, 20-lane interior shooting range 100-yard, multi-lane outdoor range Class A burn structures Class and gun cleaning room

SOURCE: CITY OF SUGAR LANDCOMMUNITY IMPACT

abatement in 2018, Wolf said. Phase 1 was completed in 2019, meanwhile Phase 2 was completed in 2025, he said.

• Tour our model home: 5206 Eloise Harper Lane Rosenberg, TX 77471

FIND YOUR HOME

Looking ahead

36

69

training and an academy to host training—will be brought to City Council for future consideration, likely after the next general obligation bond, Wolf said.

Phase 3 design is expected to take one year to complete followed by a year for construction, Wolf said. Phases 4 and 5—which will include driving pad for vehicle