Cedar Park - Far Northwest Austin | November 2025

Transportation

BY STEVE GUNTLI

Upcoming projects

Leander

1 New Hope Drive expansion Project: This will complete the design for the expansion of the west end of New Hope Drive from RM 1431 to Lakeline Boulevard. Update: The project is in the design phase • Timeline: Expected completion summer 2027 • Cost: $1.8 million • Funding source: 2022 transportation bond 2 Toro Grande Boulevard expansion Project: The north section from RM 1431 to New Hope Drive will receive intersection and signal improvements, turn lanes and utility upgrades. The south section will connect RM 1431 south and west to Parmer Lane, and extend Toro Grande Boulevard from Whitestone Boulevard to New Hope Drive. Update: Contractors have been selected • Timeline: Expected completion spring 2027 • Cost: $36.5 million • Funding source: 2022 transportation bond 3 183A Toll at Scottsdale dedicated U-turn Project: This project will shift through-lanes west and construct a new right turn lane at Scottsdale Drive. Update: Recommendation for professional engineering services were approved by council Sept. 11. • Timeline: Expected completion winter 2027 • Cost: $1.3 million • Funding source: 2022 transportation bond 4 Intersection improvements from Whitestone Boulevard to 183A Toll Project: This project will improve vehicular, cyclist and pedestrian safety. Update: Pre-design phase • Timeline: Expected completion winter 2026 • Cost: $2.57 million • Funding Source: 2022 transportation bond

183A TOLL

3

TORO GRANDE BLVD.

SCOTTSDALE DR.

183

2

1431

4

1

VISTA RIDGE BLVD.

183

734

6

.

ANDERSON MILL RD.

AVERY RANCH BLVD.

STAKED PLAINS DR.

Cedar Park

5

45 TOLL

MAP NOT TO SCALE

N TM; © 2025 COMMUNITY IMPACT CO. ALL RIGHTS RESERVED.

620

5 Lakeline Boulevard Expansion Project: The project will widen the roadway from Staked Plains Drive to FM 734 and add new shared-use paths and intersection improvements. Update: Expected to begin construction summer 2027 • Timeline: Expected completion summer 2029 • Cost: $24 million • Funding source: Capital Area Metropolitan Planning Organization grant

Ongoing projects

6 183A Toll frontage roads Project: This project will add two lanes on either side of 183A Toll from E. Whitestone to Avery Ranch Boulevard. Update: Project construction began this summer • Timeline: Expected completion 2029 • Cost: $139 million • Funding source: Texas Department of Transportation