Lake Houston - Humble - Kingwood Edition | March 2025

Transportation

BY HANNAH BROL

Upcoming projects

TOWNSEN BLVD.

MANNING RD.

TOWNSEN BLVD.

2

1 South Houston Avenue widening, reconstruction Project: This project will widen South Houston Avenue between Will Clayton Parkway and Atascocita Road from the existing two-lane asphalt roadway to a three-lane concrete roadway with curb and gutter. The project will also include a new trac signal system and drainage improvements, including the installation of underground storm sewers, inlets and ditch regrading. Update: Surveying is complete and engineering for the project was 10% complete as of the January 2025 monthly report from the city of Humble’s Public Works Department. • Timeline: January 2026-January 2028 • Cost: $1,132,360 • Funding source: City of Humble 2 Meek and Manning roads paving, drainage improvements Project: This project will repave existing asphalt streets including Meek Road and Manning Road between North Houston Avenue and Townsen Boulevard. The project will also include the installation of roadside drainage culverts, new water lines and re hydrants along Meek Road. Update: Surveying is complete and engineering for the project was 10% complete as of the January 2025 report.

UPPER LAKE DR.

59

MEEK RD.

N. HOUSTON AVE.

1960

Humble

N. HOUSTON AVE.

F I RSTST.

1960

1960

TIMBER FOREST DR.

3

WILL CLAYTON PKWY.

1

59

CAROLYN CT.

S. HOUSTON AVE.

• Timeline: August 2025-January 2026 • Cost: $241,750 • Funding source: City of Humble 3 McDugald Road, Sharon Drive and Carolyn Court reconstruction Project: This project will replace existing asphalt streets with concrete curb and gutter including

McDugald Road, Sharon Drive and Carolyn Court. The project will also replace water lines and re hydrants along McDugald Road. Update: Surveying is complete and engineering for the project was 30% complete as of the January 2025 report. • Timeline: August 2025-May 2026 • Cost: $369,500 • Funding source: City of Humble