Transportation
Ongoing projects
2243
2
183
Leander
1
2 Raider Way/Woodview Drive widening
183A TOLL
MAP NOT TO SCALE N
Project: Plans include widening the existing road to three lanes with safety improvements as well as the addition of a roundabout and a new trac signal. Update: Construction started Aug. 15. Two-way trac on Raider Way will continue through the 2023-24 school year to reduce disruption in school activity. • Timeline: August2023-August 2025 • Cost: $8million • Funding source: city of Leander
Leander
Grove Lane in Leander will connect to Raider Way, providing a secondary exit for residents. Update: Previously set to begin in early 2023, this project was delayed due to a lack of funding. • Timeline: 2025
Upcoming projects
1 Yaupon Grove Lane extension Project: The Crystal Springs neighborhood road Yaupon
• Cost: $400,000 (estimated) • Funding source: city of Leander