DEVELOPMENT BRIEFS
Projects underway in your community
COMPILED BY BROOKE SJOBERG
Switch data center completion expected in mid-summer 2024 All site work for the Switch data center under construction adjacent to the Dell Technologies campus is planned for completion next summer. In a nutshell: Bradley Dushkin, Round Rock’s assistant director of planning and development, said construction crews began work in March 2022 on the site for the future Switch data center, which is expected to be occupied by the end of 2024. The backstory: Switch is a high-performance computing technology infrastructure com- pany based out of Las Vegas, and its Tier 5 data center in Round Rock will constitute the company’s fth campus, called The Rock. Once complete, The Rock will be part of a large ecosystem of Switch campuses in Texas that will total more than 2 million square feet and 185 megawatts of power, according to informa- tion from the company.
Gattis School Road property redevelopment approved The redevelopment of a residential property at 201 Gattis School Road, Round Rock, will see a former residential property become a mixed-use development following approval from city ocials. What happened? City Council approved the rezoning of the 0.91-acre property July 13 at the request of developer Ravi Kaey, who seeks to redevelop the property. Timelines are not yet available, and it is unclear what kind of development it will be. The takeaway : The property is adjacent to a two-story apartment complex to the west with single-family homes to the east, said Brad Wiseman, Round Rock’s planning and development services director.
The Switch data center in Round Rock will be the Las Vegas company's fifth campus.
35
DELL WAY
45 TOLL
N
What they’re saying: Robert Elliott, Switch senior vice president of government and public aairs, said the project represents “hundreds of millions of [dollars of] investment.” He also said the project is anticipated to create over 100 temporary and permanent positions. Those positions will include Switch employees who will run the facility, co-located clients of the company and construction jobs.
35
N
SAVE UP TO 50% ON SELECT TEMPUR-PEDIC AND iCOMFORT CLOSEOUT MATTRESSES
0% FINANCING FOR UP TO 5 YEARS OUR BIGGEST CLEARANCE SALE OF THE YEAR!
FREE DELIVERY SETUP & REMOVAL
TWINS STARTING AT $ 119 QUEENS STARTING AT $ 179
*With $699 purchase or more. Not valid with any other offer.
FactoryMattressTexas.com
Pressure relief with gel-infused memory foam TWIN WAS $ 369 • NOW $ 239 QUEEN WAS $ 469 • NOW $ 299 SAVE $ 170 UP TO
SCAN CODE FOR LOCATIONS IN AUSTIN & SAN ANTONIO
A portion of every sale will be donated to AUSTIN/SAN ANTONIO PETS ALIVE!
15
ROUND ROCK EDITION • AUGUST 2023
Powered by FlippingBook