Conroe - Montgomery Edition | September 2025

Transportation

BY LIZZY SPANGLER

Ongoing projects

SHEPARD HILL RD.

LONE STAR PKWY. from the Texas Department of Transportation. • Timeline: first quarter 2025-fourth quarter 2025 • Cost: $3.3 million • Funding source: state funds 2 I-45 high occupancy vehicle lane extension Project: I-45 is undergoing an extension of its HOV lane between FM 1488 and South Loop 336. Update: Per an Aug. 5 update from TxDOT, this project is 60% completed. • Timeline: second quarter 2025-fourth quarter 2025 • Cost: $1.26 million • Funding sources: federal, state funds 3 Hwy. 105 widening 149 1 Hwy. 75 reconstruction Project: Between South Loop 336 North and Gladstell Street, Hwy. 75 is undergoing reconstruction. Update: This is 60% complete, per an Aug. 5 update Project: Between 10th Street and South Loop 336, Hwy. 105 is being widened from two to four lanes. Update: This project is 43% completed, per an Aug. 5 update from TxDOT. • Timeline: March 2023-second quarter 2028 • Cost: $52.65 million • Funding source: state funds 4 South Loop 336 widening Project: Between I-45 and Ladera Creek Trace, South Loop 336 is being widened from two to four lanes. Update: This project is 34% completed, per an Aug. 5 update from TxDOT. • Timeline: November 2024-third quarter 2027 • Cost: $20.57 million • Funding source: state funds 5 I-45 LED installation Project: Between FM 830 and Shepard Hill Road, high- mast LED poles are being installed along I-45. Update: This project is 37% completed, per an Aug. 5 update from TxDOT. 149

Willis

Montgomery

6

1097

BLUEBERRY HILL

LAKE CONROE HILLS DR.

LAKE CONROE

75

5

830

2432

1484

1484

105

1097

336

Conroe

7

ATKINS CREEK

2854

1

LADERA CREEK TRACE

3

BUFFALO SPRINGS DR.

GLADSTELL ST.

10TH ST.

SGT ED HOLCOMB BLVD.

4

FISH CREEK THOROUGHFARE

45

3083

2

1314

WEST FORK SAN JACINTO RIVER

1488

MAP NOT TO SCALE N

• Timeline: February 2025-first quarter 2026 • Cost: $1.45 million • Funding source: state funds 6 FM 1097 widening

• Cost: $20.21 million • Funding sources: federal, state funds 7 FM 1097 Atkins Creek project Project: At FM 1097 and Atkins Creek, a project is underway that includes culvert replacement. Update: This project is 4% completed. • Timeline: third quarter 2025-third quarter 2026 • Cost: $4.41 million • Funding sources: federal, state funds

Project: FM 1097 is being widened from two lanes to four lanes west of Blueberry Hills Road to Lake Conroe Hills Drive. Update: Per an Aug. 5 update from TxDOT, this project is 79% completed. • Timeline: second quarter 2022-second quarter 2026

Your Social Calendar, Simplified! Visit Community Impact’s new events calendar to attend local happenings, explore hobbies, and meet people.

saturday, october 4 JOIN US FOR OUR OFFICIAL FOLLOWED BY groundbreaking ceremony bring your own chair ACTIVITIES | FOOD | FAMILY FUN 4:00 - 7:00 p.m. LOCATION THE CHURCH AT MONTGOMERY FUTURE HOME CORNER OF CLEPPER AND C.B. STEWART DRIVE

MORE INFO AT twmc.org/fallfest

Start Exploring Today!

27

CONROE - MONTGOMERY EDITION

Powered by