BY JAMES T. NORMAN
Update: City Council approved the project’s design con- tract in February, with the plan 30% reviewed as of May. • Timeline: bidding to come in 2026 and construction to start in 2027 • Cost: $500,000 • Funding source: city’s capital project funds 4 TxDOT intersection improvements Project: Intersections on the docket include A Hwy. 96 and FM 270, B Hwy. 96 and Columbia Memorial Parkway. The project will include work to extend turn lanes and rebuild traffic signals. Update: design contract approved in May • Timeline: bidding to come in 2026 and construction to start in 2027 • Cost: $2.68 million • Funding source: city funds design, TxDOT funds construction 5 Hwy. 3 and FM 518 intersection Project: Work is aimed at improving mobility for future traffic. Update: Staff has reviewed a traffic study. The project’s design is completed and the city is waiting for approvals from TxDOT. • Timeline: funding should be available in fiscal year 2025-26 • Cost: $5.3 million • Funding source: League City’s 2019 bond program
asphalt overlay on seven roads. Update: The project was completed as of June. • Timeline: Work began in late 2024 and wrapped up in the spring • Cost: $1.9 million • Funding source: from the tax reinvestment fund that is part of the city’s capital improvement budget 9 Highway 3 and Highway 96 intersection Project: improvements to the intersection included additional left- and right-turn lanes to help with mobility Update: Work is done. Officials are currently cleaning up the site. • Timeline: Construction was completed in February. • Cost: $1.6 million • Funding source: Galveston County’s 2018 bond election 10 West Walker Street improvements Project: includes installing three new traffic signals along West Walker Street Update: Work was completed earlier this year. • Timeline: Completed in spring 2025 • Cost: $3.3 million • Funding source: almost all from tax increment reinvestment zone funding
Ongoing projects
6 Reconstruction of Butler Road and Turner Street
Project: The project is being carried out in two phases and involves roadway improvements and reconstructing the asphalt roadway, as well as waterline work. Update: Work is currently ongoing • Timeline: project expected to be done in July 2026 • Cost: $6.12 million • Funding source: city’s reinvestment fund 7 League City Parkway right-turn lane Project: includes adding an eastbound right-turn lane that stretches from around Butler Road to the I-45 frontage road Update: the bid for the project was awarded in April • Timeline: construction is set to be done in 2026 • Cost: $1.4 million • Funding source: Galveston County bonds
Completed projects
8 Package 7 asphalt work Project: This project took place in the northern part of the city on and around Lakeside Drive and included
YOUR DREAM HOME AWAITS NEW HOMES IN HOUSTON
CUSTOMIZABLE FLOOR PLANS CREATED WITH YOU IN MIND
HOMES FROM THE MID $500s
CALL TO LEARN ABOUT OUR LIMITED TIME SPECIAL INCENTIVES! (281) 306-5906
SCAN FOR MORE INFO
©2022 The Drees Company. All Rights Reserved. 25-2687-129 3/25
13
BAY AREA EDITION
Powered by FlippingBook