Prosper - Celina | May 2025

Paving the way From the cover

The big picture

million looking to address roads alone. “With the growth that we’re experiencing and all the growth that is surrounding us, there is just a need to expand the existing roads to accommodate it,” Prosper Engineering Director Hulon Webb said.

the future. Celina has a ve-year capital improvement plan with over $750 million dedicated to projects, many of which focus on roads. Meanwhile in Prosper crews have started the ground work on a potential November bond with $80 million to $90

As new residents pour into the area, Prosper and Celina are paving the way for growth with hundreds of millions of dollars committed in road projects. Both cities use their bond funds to address the transportation needs of the area and also look to

Road projects

E. OUTER LOOP

1 Dallas North Tollway expansion ($459.7M) Timeline: completion fall 2027 Celina 2 Parvin Road widening ($6.21M) Timeline: completion January 2026 3 Coit Road to Frontier Parkway expansion ($1.75M) Timeline: completion July 2026 4 Coit Road improvements ($3.76M) Timeline: completion June 2027 5 Coit Road reconstruction ($15.91M) Timeline: completion July 2026 6 Ownsby Parkway construction ($13.12M) Timeline: completion June 2025 7 Choate Parkway expansion ($10.44M) Timeline: completion June 2026 Prosper 8 First Street from Stuber Elementary to 9 Legacy Drive widening ($11.43M) Timeline: completion winter 2025 10 Coit Road Phase 1 expansion ($23.64M) Timeline: completion winter 2026/27 11 First Street to Coleman Street expansion ($21.79M) Timeline: completion summer 2027 DNT construction ($30.89M) Timeline: completion fall 2025

Celina

7

428

4

CHOATE PKWY.

OWNSBY PKWY.

5

1

6

83

3

FRONTIER PKWY.

1385

2

PARVIN RD.

E. PROSPER TRL.

Prosper

10

8

COUNTY RD.

FIRST ST.

11

9

380

423

DNT TOLL

N

SOURCE: CITY OF CELINA, TOWN OF PROSPERCOMMUNITY IMPACT

Ceremony Location: The Gazebo Reception: The Landing Details: 12 | 7 hour rental Up to 250 Guests Twilight Package

Myers Park & Event Center | 7117 County Road 166 | 972-548-4792

24

COMMUNITYIMPACT.COM

Powered by