Transportation
BY GRANT CRAWFORD
Upcoming projects
110
Round Rock
1 Gattis School Road Segment 6 Project: reconstructing the existing four-lane roadway to six lanes with a median, intersection and pedestrian improvements from Via Sonoma Trail to Red Bud Lane Update: construction contract awarded in November • Timeline: late 2025 or early 2026 to spring 2028 • Cost: $20.45 million • Funding sources: municipal bonds and sales tax revenue 2 Greenlawn Boulevard Project: reconstructing Greenlawn Boulevard from an existing four-lane divided roadway to a six-lane divided urban roadway with pedestrian and lighting improvements Update: construction contract awarded; work expected to begin by end of 2025 • Timeline: completion expected in summer 2027 • Cost: $13.95 million • Funding source: type B sales tax revenue
1
1431
35
4
8
5
CHISHOLM TRAIL RD.
A.W. GRIMES BLVD.
KENNEY FORT BLVD.
130 TOLL
6
CREEK BEND BLVD.
VIA SONOMA TRL.
79
3
WYOMING SPRINGS DR.
GATTIS SCHOOL RD.
9
620
7
45 TOLL
Ongoing projects
GREENLAWN BLVD.
MOPAC
2
3 Chisholm Trail South Project: full reconstruction of Chisholm Trail Road from Sam Bass Road to RM 620, with drainage, pedestrian, and lighting improvements Update: construction is underway as of July 1. Pedestrian improvements are under design. • Timeline: summer 2026 • Cost: $4.26 million for construction • Funding source: type B sales tax revenue 4 Old Settlers Boulevard Extension Project: connecting Red Bud Lane to CR 110, creating a new four-lane roadway with a center median and twin bridges over McNutt Creek Update: construction is underway and approximately 35% complete • Timeline: completion expected in spring 2026 • Cost: $23.4 million • Funding sources: sales tax revenue, municipal bonds, Williamson County Road Bond Program 5 Red Bud Lane North Project: expanding the existing two-lane roadway to a four-lane road with an intersection Update: construction is underway and approximately 10% complete • Timeline: completion expected in spring 2027 • Cost: $34.7 million • Funding sources: developer contributions, sales tax revenue, municipal bonds 6 Wyoming Springs Segment 1 Project: constructing a new four-lane roadway with shared use paths, extending from Creek Bend Boulevard to Old Settlers Boulevard Update: construction began in December 2024 and is approximately 25% complete • Timeline: completion expected in fall 2026 • Cost: $25.9 million • Funding source: sales tax revenue
MAP NOT TO SCALE N
Upcoming projects
Ongoing projects
7 Kenney Fort Boulevard Segments 5 & 6 Project: connecting Old Settlers Boulevard to University Boulevard with a six-lane roadway and median Update: under design with 60% completion of design • Timeline: construction expected to begin in late 2026 or 2027 • Cost: $4.5 million for design • Funding sources: Sales tax revenue and municipal bonds
9 Gattis School Road Segment 3 Project: expanding the existing four-lane roadway to a six-lane divided road with updated pedestrian paths and turn lanes Update: construction is underway with paving expected to take place in late 2025 • Timeline: completion expected in 2026 • Cost: $33 million • Funding sources: municipal bonds, sales tax, Texas Department of Transportation loan
Update: construction is substantially complete and the roadway is open to traffic. • Timeline: completion was expected to be complete in spring 2026 • Cost: $6.77 million • Funding source: type B sales tax revenue
Completed projects
8 Chisholm Trail North Widening Project: widening the remaining two-lane road section to match the existing five-lane section from North Chisholm Trail to South I-35