Georgetown Edition | February 2026

BY GRACIE WARHURST

2014 City identifies need for repair or replacement of bridges due to deterioration and increased traffic

2021 Voters approve mobility bond to fund bridge projects

2026 Vehicular bridges expected to be complete in spring

How we got here

1940 Austin

1999 Bridges eligible for National Register of Historic Bridges

2007 Georgetown assumes ownership of bridges from Texas Department of Transportation

2013 TxDOT implements load restrictions on bridges

2016 Study and design for bridges rehabilitation begins; identifies need for separate pedestrian bridges

2023 Vehicular bridges construction begins

2025 City Council selects a new design for pedestrian bridges

2027 Pedestrian bridges expected to be complete in summer

Avenue bridges constructed

SOURCE: CITY OF GEORGETOWN/COMMUNITY IMPACT

What’s next

cost $8 million. City officials are brainstorming temporary solutions for pedestrian access to cross the rivers before the pedestrian bridges begin construction, according to city documents.

Keith Hutchinson said there’s not a set timeline for construction but that it will begin after the pedestrian and bicycle bridges are finished. Funded by the Georgetown Transportation Enhancement Corp. sales tax, the project will

The roundabout project at San Gabriel Village Boulevard is designed to reduce speeds and improve visibility, according to city documents. Design for the project is 60% complete, officials said. In a statement, Communications Manager

CRIME DOESN’T PAY CRIMESTOPPERS DOES!

WCCS partners with local school districts through the Safe Schools Program. Students are encouraged: SEE SOMETHING HEAR SOMETHING SAY SOMETHING Help fight crime in Williamson County — your tip can make a difference. Anonymous tips leading to arrest can earn up to a $5,000 cash reward. Submit tips anonymously: 1-800-253-7867 www.wilcocrimetips.org • P3Tips App