Frisco | January 2025

Transportation

BY SAMANTHA DOUTY

Upcoming projects

UNIVERSITY DR.

380

PGA PKWY.

6

1 Teel Parkway widening Project: The project will widen Teel Parkway from two lanes to four lanes from Stafford Middle School to Olive Branch Drive. Update: The project is in the design phase and construction is expected to start later this year. • Timeline: mid 2025-end of 2026 • Cost: $10 million Project: The construction will widen and reconstruct the roadway from Lebanon Road to Stonebrook Parkway and Stonebrook from Legacy Drive to 4th Army Drive. Update: The project is in the planning phase with construction expected to start next year. • Timeline: mid 2026-mid 2027 • Cost: $15 million • Funding source: city of Frisco 3 Ohio Drive at Wade Boulevard roundabout Project: A new roundabout will be added to the corner of Ohio Drive and Wade Boulevard. Update: The project is currently in the planning phase. • Timeline: early 2026-early 2027 • Cost: $4 million • Funding source: city of Frisco • Funding source: city of Frisco 2 Legacy Drive widening

ROCKHILL PKWY.

OLIVE BRANCH RD.

VIRGINIA PKWY.

1

4

5

WESTRIDGE BLVD.

LEWISVILLE LAKE

PANTHER CREEK PKWY.

2478

HILLCREST RD.

ELDORADO PKWY.

7

289

KING ST.

MAIN ST.

Frisco

GARTNER RD.

DNT TOLL

STONEBROOK PKWY.

ROLATER RD.

423

3

WADE BLVD.

4TH ARMY DR.

2

LEBANON RD.

SRT TOLL

GAYLORD PKWY.

WARREN PKWY.

MAP NOT TO SCALE N

SRT TOLL

• Cost: $56.4 million • Funding source: city of Frisco, Collin County 5 Hillcrest Road construction

in late 2024. • Timeline: late 2024-mid 2026 • Cost: $11.03 million • Funding source: city of Frisco

Ongoing projects

Project: The project will create a four-lane divided roadway between PGA and Panther Creek parkways. Update: The project is under construction and will be completed later this year. • Timeline: early 2024-September 2025 • Cost: $5.99 million • Funding source: city of Frisco 6 Mahard Parkway construction Project: The project will construct a six-lane roadway from PGA Parkway to US 380. Update: The project is under construction after bidding

4 Panther Creek Parkway construction Project: The project runs from Dallas North Tollway to Preston Road. The project will create a new six-lane roadway to fill the last remaining gap of Panther Creek Parkway in Frisco. Update: The contractor is working on improvements to the storm drain, water line and sanitary sewer line. Roughly 70% of the improvements to the storm drainage infrastructure is complete, according to a January engineering report. Paving is anticipated to begin early this year. • Timeline: early 2024 - end of 2025

Completed projects

7 Gartner Road traffic signal installation Project: A new traffic signal was added to the intersection of Main Street and Gartner Road. Update: The light was activated in December. It will serve the existing Grove neighborhood on the south side of Main Street and the future Grove neighborhood. • Timeline: mid 2024-end of 2024 • Cost: $250,000 • Funding source: city of Frisco

7797 Stonebrook Pkwy, Frisco, TX 75034 | (972)334-0005

FRISCO & TEXAS HOMEOWNERS ASSOCIATION MANAGEMENT

Serving children ages 2-5

PARTNER WITH US FOR YOUR COMMUNITY MANAGEMENT FOR THE HOLIDAYS. Call Today and See How You Can Earn $300 for YOUR COMMUNITY . HOLIDAY SPECIAL

ASK LJ “THE HOA LADY” Your Community HOA Management Partner of Choice for Single Family, Condos, Townhomes, Investors & Developers

NOW ENROLLING FOR FALL! • Low teacher/student ratios • Specializing in Kindergarten Readiness Learn more at www.applecreekpreschool.com

972-283-2539 • info@hoa.homes TexasHOAMgmt.com Women, Christian, Veteran-Owned in Frisco, TX

10

COMMUNITYIMPACT.COM

Powered by