BY JESSICA SHORTEN
In their words
Stay tuned
The other major factor will be the reconstruction to widen the Hwy. 290 overpass at Skinner Road, which will potentially cause additional trac delays. Additionally, work to widen the Grand Parkway from Hwy. 249 to Hwy. 290 will also likely intersect with the timeline for the Greenhouse Road work, Eric Heppen, director of engineering at Harris County Precinct 3, said.
Multiple ocials said they anticipate the most intensive portion of construction will be constructing a tunnel-like underpass structure beneath the Union Pacic railroad which runs parallel to Hwy. 290. “The project will entail going under the railroad and any time that has to happen there will be a lot of steps to get to the nish line,” Martone said.
“This project will transform the way trac travels around the US 290 corridor in Cypress.”
TOM RAMSEY, HARRIS COUNTY PRECINCT 3 COMMISSIONER
Greenhouse Road construction
2028 January: Hwy, 290 overpass reconstruction complete December: Barker Cypress overpass reconguration bid process starts
2030 December: Estimated nal completion date of pedestrian crossings and sidewalks, light timing.
“Any time we can alleviate trac o of Barker Cypress [Road] and Fry Road, it is a good thing.” LESLIE MARTONE,
2027
2026 February: Estimated Greenhouse Road construction bid date April-June: Potential Greenhouse Road construction start
2029 January: Barker Cypress overpass reconguration project construction start
2031
CYFAIR CHAMBER OF COMMERCE PRESIDENT
SOURCE: HARRIS COUNTY PRECINCT 3, HARRIS COUNTY MUD 500COMMUNITY IMPACT