Pflugerville - Hutto Edition | April 2022

TRANSPORTATIONUPDATES Construction begins at Puger FarmLane and Town Center Drive

COMPILED BY CARSON GANONG

ONGOING PROJECTS

The intersection of Puger Farm Lane and Town Center Drive was closed in March and will remain closed for approximately two months while construction of a roundabout takes place. The construction is the rst phase of a larger road project in connection with Lifestyle Communities, a nearby 1,050-unit residential development. For the duration of the closure, Stone Hill Park will be accessible from the west through the Highland Park neighborhood. Additionally, Century Stone Hill North Apartments and Century Stone Hill South Apartments will have access via the Highland Park neigh- borhood to and from their driveway on Town Center. Residents of Stone Hill Luxury Apartments and Century Stone Hill South Apartments will have access to and from the south via Puger Farm,

130 TOLL

N

Impact Way extension in Pugerville Pugerville City Council approved a $2.4 million construction contract with Joe Bland Construction L.P. on March 22 for a project extending Impact Way. The project will add ap- proximately 940 feet of new roadway with sidewalks to Impact Way along with 750 feet of water lines and four retention walls. Timeline: TBD Status: $2.4 million Funding source: city of Pugerville

Project construction at the intersection of Puger Farm Lane and Town Center Drive should be complete by May. (Carson Ganong/Community Impact Newspaper)

according to city information. Future phases will involve extend- ing Puger Farm further north and should not cause any road closures, according to city sta. Timeline: March-May (for the roundabout) Cost: $3 million Funding source: Lifestyle Communities

130 TOLL

TOWN CENTER DR.

130 TOLL

N

N

FM 685 corridor study in Pugerville On March 8, Pugerville City Council approved a $1 million agreement for professional engineering services with Kimley-Horn and Associates Inc. in connection with a comprehensive analysis of the FM 685 corridor. The study was included in a 2020 transportation bond. Timeline: March 2022-January 2023 Cost: $1.03 million Funding source: city of Pugerville

GrandAvenue Parkway reconstruction tomove into next phase of project inApril A reconstruction project on a section of Grand Avenue Parkway will move The rst phase, which 45 TOLL

shifted to the southbound side of Grand Avenue, with one lane going in each direction. Trac will similarly shift to the northbound side when Phase 2 begins.

began in December, involves reconstruction of the roadway’s northbound lanes between Viki Lynn Place and Ramble Creek Drive. The second phase will involve reconstruction of southbound lanes on the same section of the road. Trac is currently

into its second of four phases in early April. The reconstruction is necessary to repair damage from previous roadwork in 2017 that resulted in numerous pavement failures, according to city documents.

35

PICADILLY DR.

Timeline: December 2021-summer 2022 Cost: $2.76 million Funding source: city of Pugerville

ALL INFORMATION ON THIS PAGE WAS UPDATED AS OF MARCH 25. NEWS OR QUESTIONS ABOUT THESE OR OTHER LOCAL TRANSPORTATION PROJECTS? EMAIL US AT PFHNEWSCOMMUNITYIMPACT.COM.

GRAND AVE. PKWY.

N

So�est & Purest Water for your Home and Family!

“ Not all Water So�eners are created equal! Flow rates, and proper sizing is important to combat our hard water here in Central Texas. Our Refiner 4, the most advanced home filtration system on the market today and is designed to combat unwanted chemicals and impurities in our water. Did you know?

Best in Class Energy Efficient

Locally owned � ALL SYSTEMS ARE 100% CERTIFIED AND MADE IN USA � Founded and approved by plumbers

13

PFLUGERVILLE  HUTTO EDITION • APRIL 2022

Powered by