Keller - Roanoke - Northeast Fort Worth | May 2026

Transportation

BY HEATHER MCCULLOUGH

encounter moving interior-lane closures as progress continues south toward North Richland Hills. Work in

Ongoing projects

114

DORMAN RD.

Keller is expected to finish in June. • Timeline: March-summer 2027 • Cost: $9.9 million

1 North Oak Street updates Project: Roadwork on North Oak Street will be from Byron Nelson Boulevard to Dorman Road and include a 31-foot curbed roadway, installation of new storm drain infrastructure and cross culverts to replace the existing open ditches. Additional work includes the replacement of water and sewer lines and the addition and replacement of sidewalks. Update: The project is in the design phase and will take at least six months to complete after design work began in April. • Timeline: designs to finish in 6-8 months from April • Cost: $411,530 • Funding sources: city of Roanoke, Denton County 2 FM 1938 median project Project: The work will include converting the road’s two-way left-turn lane into a 14-foot-wide raised median. At intersections with median breaks, the median will be reduced to a width of 2 feet, and a 12-foot-wide left-turn lane will be created. The project will be from Southlake Boulevard to Emerald Hills Way, and lane configuration will not change. Additionally, the road from FM 1709 to Starnes Road will be reconstructed. Update: Workers moved into Keller, and drivers will

BYRON NELSON BLVD.

GOLDEN TRIANGLE BLVD.

35W • Funding source: Texas Department of Transportation 3 Ray White Road widening improvements Project: Ray White Road will be widened to a four-lane divided road between Mirage Drive and the bridge over Bear Creek. HERITAGE TRACE PKWY. ALTA VISTA RD. Additional improvements include adding a sidewalk on both sides of the road, installing street lights, storm drain improvements and constructing modifications to the roundabout at Ray White Road and Park Vista Boulevard Update: The main lanes and roundabout modifications are now paved. The contractor is in the process of pouring sidewalks and finalizing the installation of streetlights and the traffic signal at Wall Price. • Timeline: expected to finish late summer, early fall • Cost: $22 million • Funding source: city of Fort Worth TARRANT PKWY.

1

377

Roanoke

KROGER DR.

SHADY GROVE RD.

RAY WHITE RD.

3

1938

N. TARRANT PKWY.

MIRAGE DR.

377

BASSWOOD BLVD.

2

WATAUGA RD.

Keller

26

183

EMERALD HILLS WAY

N

Powered by