BY AMANDA CUTSHALL
Zooming out
How we got here
Parks and Recreation Director David Lopez said Gregg-Clarke Park will continue to be a cornerstone of Kyle. “We’re building something that not only serves today’s residents, but will inspire and activate the next generation of athletes, families and neighbors,” he said. A closer look at Kyle’s Gregg-Clarke Park Other planned improvements in various stages of design include: Splash pad and swimming pool upgrades More community meeting spaces Balleld redesigns for regulation-level play New playground Accessibility updates
The grind to Kyle Skatepark Kyle ocials paused construction in spring 2024, terminating the initial $1 million design-and-build agreement with Spa Skateparks as new leadership evaluated the plan. Council restarted the project in September 2024 with a new construction contract and an expanded, all-wheels design.
November 3, 2020 Voters approve $1 million park bond
February 21, 2023 Council approves contract with Spa Skateparks
May 2023-March 2024 Public engagement and design approval
May 2024 Permitting and early site work starts
October 24, 2025 Groundbreaking ceremony
Summer 2026 Expected completion
SOURCE: CITY OF KYLE, SPA SKATEPARKSCOMMUNITY IMPACT
SOURCE: CITY OF KYLECOMMUNITY IMPACT
21
SAN MARCOS BUDA KYLE EDITION
Powered by FlippingBook