Transportation

BY AMANDA CUTSHALL

967

CULLEN BLVD.

45 TOLL

Buda

Upcoming projects

AUSTIN ST.

JACK C. HAYS TRAIL

35

REMUDA TRL.

1 RM 967 deceleration lanes Project: deceleration lanes will be added in two locations: A Garlic Creek Drive at Remuda Trail B Garlic Creek Drive at Grove Lane Update: in nal construction plans

GROVE LN.

3

San Marcos

1A

N. JOHNSON AVE.

CULLEN BLVD.

1B

35

SAN ANTONIO ST.

967

2001

12 45 TOLL

GARLIC CREEK DR.

2

AUSTIN ST.

W. SAN ANTONIO ST.

• Timeline: 2021-TBD • Cost: $2.57 million • Funding source: 2021 Buda bond

Buda

PITT ST.

2770

WINDY HILL RD.

2001

HOPKINS ST.

2 Austin Street reconstruction Project: parking, sidewalks and stormwater improvements from FM 2770 to San Antonio Street Update: design phase is 60% complete • Timeline: 2021-TBD • Cost: $8.6 million • Funding source: 2021 Buda bond 3 Bishop and Belvin Street improvements Project: full-depth road reconstruction with drainage, water, wastewater, retaining walls and sidewalk improvements from Belvin Street to West San Antonio Street Update: design phase is 90% complete; acquisition process underway 150 • Timeline: 2026-28 • Cost: $11.26 million • Funding source: Capital Improvement Program; city utility and general funds BLANCO RIVER

WONDER WORLD DR.

SA

35

2001

SAN MARCOS RIVER

6A

4

123

KYLE PKWY.

N. MAIN ST.

SIX CREEK BLVD.

35

WINDY HILL RD.

6B 6C 6D

2001

21

BUNTON CREEK RD.

5

OLD STAGECOACH RD.

Kyle

RATTLER RD.

MAP NOT TO SCALE N

35

5 Old Bastrop Road widening Project: Old Bastrop Road from Rattler Road to Centerpoint Road will be widened and a 16-inch water main will be added Update: water main installed in September; waterline crossing underway • Timeline: 2025-26 • Cost: TBD • Funding source: 2025 road project certicates of obligation 6 Old Stagecoach Road widening and Center Street improvements Project: Old Stagecoach Road will be widened to a four-lane roadway from Veterans Drive to Main Street. Work completed in four parts: Kyle 150

A North portion of Old Stagecoach Road from Veterans Drive to Six Creeks Boulevard B Old Stagecoach Road from Six Creeks Boulevard to Center Street C Center Street from Old Stagecoach Road to Veterans Drive D Three lanes from Veterans Drive to Main Street Update: in nal design phase 21

Ongoing projects

4 Kyle Parkway-Lehman Road extension Project: Lehman Road will be extended to a four-lane roadway from Bunton Creek Road to Dacy Lane; Kyle Parkway will connect with the new segment Update: design phase is 95% complete

• Timeline: 2023-27 • Cost: $41.2 million • Funding source: 2022 Kyle bond

• Timeline: 2023-27 • Cost: $42.5 million • Funding source: 2022 Kyle bond

WE SERVICE HYBRID & ELECTRIC VEHICLES | PREVENTATIVE MAINTENANCE | ALL REPAIRS AND SERVICES

BMW and MINI Repair and Service

Scan to Schedule Your Appointment

5160 Industrial Way Dr. Buda, TX | 512-856-5355 | www.atxbimmer.com

15

SAN MARCOS  BUDA  KYLE EDITION

Powered by