TRANSPORTATION UPDATES Hollywood Park plans street repair program City Council was expected to consider acting on a long-range street maintenance program at its regularly scheduled June 20 meeting. In a May 23 public forum, city engineers unveiled a report that included a review of Hollywood Park pave- ment conditions, which had been conducted in late March, and a proposed multiyear program for potential minor and major road projects. City Secretary Patrick Aten said council would use its June 20 meeting to vote on a prioritized program. According to the engineers’ report, it would take an estimated $13.2 million to repair all 53 surveyed city streets. Frank Jaster, senior project manager for consulting firm KCI Technologies, said he and his staff graded the streets, rating them excellent, good, fair, poor and failed. Jaster said Hollywood Park has no excellent or failed roads, but has many fair to increasingly poor streets, including El Portal Drive, Sunway Drive, Skyforest Drive and Meadowbrook Drive. The new street maintenance program would begin in summer 2024 and would take 10-15 years to fully imple- ment, Jaster said. Jaster said, however, minor fixes, such as sealing cracks

COMPILED BY EDMOND ORTIZ

ONGOING PROJECTS

ROAD TO IMPROVEMENT Engineers from KCI Technologies assessed and graded pavement conditions on all 53 city roads in Hollywood Park as part of the town’s plan to develop a multi-year street repair program.

WAGON TRAIL RD.

FAWN DR.

END GATE LN.

14 streets rated good 26 streets rated fair 13 streets rated poor

53 streets surveyed

N

$13.2M estimated cost for repairs 10 to 15 years to complete all fixes

ALL INFORMATION ON THIS PAGE WAS UPDATED AS OF JUNE 7. NEWS OR QUESTIONS ABOUT THESE OR OTHER LOCAL TRANSPORTATION PROJECTS? EMAIL US AT NSANEWS@COMMUNITYIMPACT.COM. End Gate Lane in July, then begin rebuilding Fawn Drive, starting in the 300 block of Fawn Drive. In all, the project will improve nine streets and five cul-de-sacs east and west of Northwest Military Highway. Timeline: June 2023-June 2024 Cost: $6.28 million Funding source: city of Shavano Park Shavano Park street improvements D&D Contractors began work in early June on Wagon Trail Road, which is being fully rebuilt through late August. D&D officials tentatively anticipate working on reconstructing

BLANCO RD.

281

1604

HOLLYWOOD PARK

N

SOURCE: KCI TECHNOLOGIES/COMMUNITY IMPACT

and replacing asphalt, could be suggested for most city streets. He added that levels of suggested road improve- ment would depend on costs, available funding sources and severity of existing problems. The assessment results can be found at www.hollywoodpark-tx.gov.

VOLUNTEER JUST 1 HOUR A MONTH!

YOUR HELP IS WANTED. Give just 1 hour a month to save at-risk seniors!

Be the bright spot in a lonely, hungry seniors day by giving just 1 hour a month! Pick up meals near you and see firsthand the joy you can bring. Learn more at mowsatx.org/saenvolunteer, scan -> -> -> -> or call 210-735-5115 or 866-80-MOWSA (6-6972).

9

NORTH SAN ANTONIO EDITION • JUNE 2023

Powered by