Transportation

BY BRITTANY ANDERSON

with completion TBD • Cost: $68.39 million • Funding source: TxDOT, city of Austin 2016 Mobility Bond 3 Oak Knoll Flood Risk Reduction Project: improvements to the storm drain system in the Oak Knoll neighborhood to reduce the risk of ooding, including new storm drain pipes and inlets on several roads and easements, and increasing the capacity of the detention pond on Chelsea Moor Update: trac control measures being placed along the construction area, potholing in progress to verify and install the waterline along Columbia Oaks Court • Timeline: completion is expected in 2027 • Cost: $9 million • Funding source: city of Austin 2018 bond 4 Spicewood Springs Road Regional Mobility Project Project: expands Spicewood Springs Road from two lanes to four lanes with a center median, shared-use paths Update: crews are working on drainage infrastructure, including retaining ponds, storm drains and rain gardens on the south side of the street • Timeline: completion expected in late 2026 • Cost: $31 million • Funding source: city of Austin 2016 Mobility Bond

Ongoing projects

Ongoing Projects

WELLS BRANCH PKWY.

BROAD OAKS DR.

1 Burnet Road Mobility Program Project: updating trac signals, improving crossings and bus stops, trail connections, curb extensions, drainage improvements, Americans with Disabilities Act-compliant shared-use paths, raised medians and more on A Burnet Road from White Horse Trail to US 183, B Bright Verde Way to MoPac and C US 183 to Bright Verde Way Update: work will begin at Burnet Road and Koenig Lane in January and continue north to approximately 500 feet south of US 183 • Timeline: construction on A expected to begin in January, construction on B is expected to begin in summer 2026, and C in the spring • Cost: $13.8 million A , $23 million B , $16 million C • Funding source: city of Austin 2016 Mobility Bond, CapMetro 2 Loop 360 Courtyard Drive/RM 2222 Project: removing trac signals from mainlanes and constructing an underpass at Courtyard Drive; reconguring RM 2222 to include a diverging diamond interchange; and adding shared-use paths and sidewalks Update: excavation ongoing on the west clis adjacent to the southbound lanes • Timeline: construction expected to begin mid-2026,

COLUMBIA OAKS DR.

3

MOPAC

JOLLYVILLE RD.

METRIC BLVD.

183

1B

WALNUT CREEK PARK

SPICEWOOD SPRINGS RD.

GREAT HILLS TRL.

5

BRIGHT VERDE WAY

360

1C

4

2222

SPICEWOOD SPRINGS RD.

2

35

CAPITAL OF TEXAS HWY.

5 North Burnet/Uptown Station Project: rail station located along North Austin’s Red Line featuring two double-length platforms, pedestrian and bike pathways, local bus route connections and safety and security enhancements

Update: full construction began in November after initially breaking ground in January 2022 • Timeline: completion expected in mid-2027 • Cost: $49.3 million • Funding source: CapMetro and Brandywine Realty Trust

1A

183

COURTYARD DR.

KOENIG LN.

WHITE HORSE TRL.