Transportation
BY CONNOR PITTMAN & MARY KATHERINE SHAPIRO
H I C K OR Y H I L L R D .
Argyle
LEWISVILLE LAKE
Upcoming Projects
407
TWIN COVES DR.
HIGHLAND SHORES BLVD.
377
Lantana
KANSAS CITY SOUTHERN RAILROAD
1
2
HIGHLAND VILLAGE RD.
BRIARHILL BLVD.
35E
JUSTIN RD.
Bartonville
D I X O N L N .
2499
BRIDLEWOOD BLVD.
E PKWY.
WAKETON RD.
4 FM 2499 and FM 3040 intersection improvements
Flower Mound
FLOWER MOUND RD.
• Cost: $42,000 • Funding source: street maintenance sales tax funds • Timeline: Sept. 12-mid-October 5 Wichita Trail Phase 2 Project: The entire project, which includes two phases, covers the reconstruction of Wichita Trail between 550 feet south of Cardinal Drive and Bayshore Drive. Update: After completing the first phase of the project, construction crews have moved onto the second phase that covers repairs between High Meadow Road and Bayshore. • Cost: $2.7 million • Funding source: street maintenance sales tax funds • Timeline: mid-September-mid-November Project: Reconfiguration to provide a dual left turn, three thru lanes, and a dedicated right turn lane for each direction of traffic. Update: Council approved an interlocal agreement with Denton County for funding. • Cost: $3.5 million • Funding sources: Denton County funds, impact fees and town capital project funds • Timeline: early 2026-late 2026
CHURCHILL DR.
3
5
WICHITA TRL.
HIGH MEADOW RD.
GRAPEVINE LAKE
3040
Westlake
4
BAYSHORE DR.
LONG PRAIRIE RD.
N
MAP NOT TO SCALE
safety from Briarhill Boulevard to Twin Coves Drive. Update: Council approved selling certificates of obligation to fund the project. • Cost: Estimated $10 million • Funding source: City and Denton County funding • Timeline: Beginning in 2026
Upcoming projects
1 Highland Village Road Project: Replacing the asphalt pavement and enhancing safety from Brazos Boulevard to Kansas City Southern Railroad. Update: Council approved selling certificates of obligation to fund the project. • Cost: Estimated $3.8 million • Funding source: City and Denton County funding • Timeline: Beginning in spring 2026 2 Highland Shores Boulevard Project: Replacing the asphalt pavement and enhancing
Ongoing projects
3 Churchill Drive Project: Concrete panel repairs along the 2700 block of Churchill Drive, west of FM 2499. Update: Construction crews began repairs in mid- September.