Check out 4 ongoing construction projects in Argyle ISD
377
Northlake
HICKORY HILL RD.
Argyle
1384
4
2
407
JUSTIN
338
Lanta
5 T H S T .
CANYON FALLS DR.
35W
Bartonville
2 Middle School No. 1 Project: The addition of the new middle school will help facilitate the district’s 10-year strategic plan. The new school will serve grades 7-8 with a capacity of 1,200 students, according to district documents. Updates: Crews are spreading topsoil and getting ready to plant grass. Trees are already planted. The tennis courts are visible as concrete slabs, and fencing has begun around them. Work is finishing up in the center portion to connect the 1 AISD stadium Project: The new stadium will include a video scoreboard, two-story press box and seating for about 7,500 people, according to the district’s website. Updates: The fencing is complete on the visitor side of the grandstands, and brick columns are in place. The video board structure is up, and all electrical boxes are set. LED panels are expected to start being installed soon. • Location: 6601 Canyon Falls Drive, Argyle • Estimated completion: Late November • Funding source: 2022 bond package
north and south classroom wings. Roofing is being installed in various areas, allowing for interior sheetrock, paint and finishes to begin soon. • Location: Located on the north side of FM 407, just east of I-35W in Argyle. • Estimated completion: summer 2026 • Funding source: 2022 bond funds 4 Elementary School No. 5 Project: The elementary school will be 104,685 square 3 Indoor activity center Project: The indoor activity center will be utilized by multiple teams and student groups that will no longer have to travel to the indoor facility at the US 377 campus. Updates: The masonry block is up all the way around the building. Crews are currently working on the veneer stone and brick. The south side has been completed, and they are now working on the east side. • Location: 6601 Canyon Falls Drive, Argyle • Estimated completion: Late December • Funding source: 2022 bond funds 156
1 3
BRID
377
Flow Mou
114
GRAPEVINE LAKE
MAP NOT TO SCALE
N TM; © 2025 COMMUNITY IMPACT CO. ALL RIGHTS RESERVED.
ROANOKE
Westlake
170
feet with two stories, 61 classrooms and the capacity for 850 students, according to previous reporting. Updates: The Argyle ISD Board of Trustees unanimously approved a guaranteed maximum price not to exceed $49.32 million for Elementary School No. 5. • Location: Located on the north side of FM 407, just east of I-35W in Argyle. • Estimated completion: Before the 2027-28 school year • Funding source: 2022 and 2025 bond funds
DCTA presents the LISD “Destination: Success” Achievement Award
Making an Impact in the Community, One Smile at a Time.
Dahiana De Andrade Guaido, an 8th Grade Student at Briarhill Middle School, was chosen for this achievement by several teachers and administrators because of her contagious smile and ability to make friends with everyone in the building regardless of their age or status.
My favorite way to give back to others is by smiling at people so that they know they are special and important.
“She accepts everyone as they are and loves them fully! We are so extremely proud of her!” - Dr. Tina Krol, Briarhill Middle School Principal
Dahiana De Andrade Guaido
10
COMMUNITYIMPACT.COM
Powered by FlippingBook