IMPROVING PLANO
Construction can be disruptive, but the end result is a better Plano. Below are major projects underway in the City of Plano over the next six months. (Start and completion dates are estimates.)
INTERSECTION IMPROVEMENTS
MEDIAN RENOVATION
Park Blvd – Country Place to Ohio Start 1/24 | Completion 4/24
Coit at McDermott Start 8/23 | Completion 4/24 Hedgcoxe at Legacy Start 8/23 | Completion 4/24 Spring Creek at Windhaven Start 8/23 | Completion 4/24 Los Rios at Jupiter Start 8/23 | Completion 4/24 18th Street at Jupiter Start 3/24 | Completion 2/25 Custer at USA Start 3/24 | Completion 2/25 Custer at Ridgeview Start 3/24 | Completion 2/25 Ohio at Park Blvd Start 3/24 | Completion 2/25
19
1 2 3 4 5 6 7 8
121
PARK RENOVATION
1
Evans Park Start 2/21 | Completion 1/24 Plano Event Center Courtyard Start 6/23 | Completion 3/24 Jack Carter Park Start 8/23 | Completion 8/24 Hoblitzelle East Park Start 1/24 | Completion 10/2424. Glen Meadows Park Start 1/24 | Completion 1/25 Longhorn Park Start 3/24 | Completion 3/25
24 23 22 21 20 25
8
2
TENNYSON PKWY
to
11 3
11
ROAD WIDENING
SPECIAL PROJECTS
Shiloh Rd – 14th St to Park Blvd Start 5/22 | Completion 3/24 Emerson Dr – Preston Meadow to Virginia Start 10/23 | Completion 6/24
Collin Creek Mall Culvert & Waste Water Improvements Start 8/21 | Completion 8/24 Plano Event Center Street & Waste Water Improvements Start 12/23 | Completion 12/24
WINDHAVEN PKWY
9 10
26
27
17
21
STREET RECONSTRUCTION Commerce St – 15th St to Plano Pkwy 11
NEW CONSTRUCTION/EXPANSION
PARKER RD
Start 9/21 | Completion 11/23 10th St – N Ave to Jupiter Start 5/23 | Completion 5/24
Carports – Rushin Police Substation & Emergency Operations Center Start 11/23 | Completion 5/24 Fire Station 5 Start 1/24 | Completion 3/25
28
25
12
29
24
29
ASPHALT OVERLAYS
PARK BLVD
3
Hedgcoxe Rd – Custer to Coit Start 8/22 | Completion 11/23 Plano Pkwy – E City Limits to Los Rios Start 8/23 | Completion 5/24 Los Rios Blvd – 14th Street to Merriman Start 8/23 | Completion 11/23 Parker Rd – Spring Creek to E City Limits Start 8/23 | Completion 5/24 Parker Rd – W City Limits to Parkwood Start 7/23 | Completion 11/23 Parkwood Blvd – Windhaven to Plano Pkwy Start 7/23 | Completion 11/23
13 14 15 16 17
18
28
For project details, visit Plano.gov/CIP
PRESIDENT GEORGE BUSH TURNPIKE
18
Listen to the City’s monthly podcast at InsidePlano.com Sign up for weekly news updates from the City of Plano at Plano.gov/News
2
COMMUNITYIMPACT.COM
Powered by FlippingBook