Main Street reconstruction completion expected by March
Ongoing projects
Ongoing projects
Ongoing projects
KAUFMAN ST.
Richardson’s Main Street reconstruction project continues this week after a three-month pause caused by delays in utility relocation, the city announced. The construction, which extends from Green- ville Avenue to just past Abrams Road, is expected to be completed in March, depending on weather conditions. What’s happening Oncor told the city it would begin moving overhead power lines underground starting early January, with its work expected to be complete in early February. After the power lines are relocated, the city can begin the next stage of construction, which will include adding sidewalks, street lights and trees along the south side of the street. New paving has largely been completed already, except for the outer southside lane, where Oncor is still working. At least one lane in each direction will remain
open during construction, although trac conges- tion may increase. The big picture The $6.5 million reconstruction project began in February 2025. Completed work includes a new dedicated turn lane onto Abrams Road, barri- er-free ramps installed at intersections, new trees and landscaping, the replacement of water, sewer and storm drainage pipes and inlets and upgraded street lighting. The project is the second phase of a larger recon- struction along Main Street. “Enhanced intersections, sidewalks, and crossings will make it easier to access nearby businesses, neighborhoods and transit DART station, supporting a more walkable, accessible and connected district as the area continues to grow into a hub for international avors and other distinctive experiences,” Richardson City Manager Don Magner said.
3A
2
1B
75
LINGCO DR. 3B
1A
JONSSON BLVD.
V E R N E
T I M B E R L A K E C
N
N
N
1 Jonsson Boulevard, Tatum Street reconstruction Project: Work includes pavement reconstruction along A Jonsson Boulevard and B Tatum Street, sidewalk repairs, water and sanitary improvements and inclusion of a bike lane. Update: Street reconstruction on the west side of Jonsson is completed. Reconstruction of the east side of Jonsson and the south side of Tatum is ongoing. Waterline installation is also ongoing. • Timeline: summer 2025-winter 2026 • Cost: $3.5 million • Funding source: city of Richardson
2 Nantucket Drive reconstruction Project: Crews will complete reconstruction of Nantucket Drive from Melrose Drive to south of Vernet Street. Update: All underground utility work has been completed, as well as reconstruction between Melrose and Provincetown Lane. Reconstruction of the northbound lane of Nantucket Drive is ongoing, followed by inlet, driveway and sidewalk concrete placement. • Timeline: spring 2025-winter 2026 • Cost: $2.2 million • Funding source: city of Richardson
3 Sherman Street reconstruction Project: Work includes road reconstruction of Sherman Street from A Kaufman Street to Lingco Drive and reconstruction of Lingco from B Sherman to Spring Valley Road. Update: Utility work is ongoing and expected to be completed by mid-January, and then paving operations will begin. • Timeline: spring 2025-summer 2026 • Cost: $6.6 million • Funding source: city of Richardson
The Main Street reconstruction project is part of a larger reconstruction plan along Main Street aimed at improving downtown infrastructure.