Transportation
BY PARKS KUGLE
TPC PKWY.
Stone Oak
CAMP BULLIS
use path, as well as drainage improvements and utility adjustments. The estimated construction start date was moved from summer 2025 to summer 2026, according to city documents. • Timeline: summer 2026-summer 2028 • Cost: $14.6 million • Funding source: 2022 General Obligation Bond and Bexar County
roadway to capture overflowing water and transport it to the Olmos Basin, raised curbs with sidewalks, dedicated bike lanes and safety buffers between bicyclists and traffic. Update: The project is currently under construction, including the construction of two 5 1/2-foot sidewalks, two 4-foot bike lanes, two 2-foot buffers, two 11-foot lanes and fresh asphalt. • Timeline: summer 2025-July 2026 • Cost: $4 million • Funding source: federal grant, with the remaining costs covered by the 2022 bond 5 SA Airport Runway 13R-31L rehabilitation Project: The project includes replacing concrete pavement sections of the runway, upgrading electrical lighting systems to energy-efficient technology and restoring pavement markings along impacted sections. Update: During the project, the San Antonio International Airport will maintain winter air traffic patterns over the northeast and southwest portions of the city, with landings and takeoffs being exclusively from the backup air carrier runway known as Runway 4/22. • Timeline: Jan. 12-March 6 • Cost: N/A • Funding source: FAA Airport Improvement Program, city of San Antonio
Upcoming projects
EVANS RD.
3B
3A
Ongoing projects
BULVERDE RD.
6
1 Vance Jackson Road (Huebner Road to Wurzbach Road) project Project: Part of the city of San Antonio’s 2022-2027 bond program, work includes a series of roadway improvements, such as adding a consistent two-way center turn lane, building improved sidewalks and a shared-use path and installing underground drainage to low-water crossings. The project on Vance Jackson Road stretches from Huebner Road to Wurzbach Road. Update: The project is currently in the design phase and is estimated to begin construction in 2027, according to city documents. • Timeline: winter 2027-fall 2028 • Cost: $16.4 million • Funding source: 2022-2027 bond program 2 Bulverde Road Phase 2 Project: Part of San Antonio’s 2022-27 bond program, Phase 2 will construct improvements on Bulverde Road from Green Spring Drive to Redland Road. These include new sidewalks, curbs, driveway approaches, drainage and bicycle facilities. The project will also address road wear and tear and an existing low-water crossing. Update: Currently in the design phase, the project will widen the road to 86 feet, expand it to four lanes, add a center turn lane, and add a sidewalk and a shared-
HARDY OAK BLVD.
281
REDLAND RD.
JUDSON RD.
REDLAND RD.
Ongoing projects
Hollywood Park
3 District 9 Pedestrian Mobility project Project: Part of the city of San Antonio’s 2022-27 bond program, the project seeks to widen pedestrian access. The project includes the construction of turn lanes, new sidewalks, driveway approaches and drainage improvements in the Stone Oak area. Update: Currently in the design phase, associated projects for District 9 include constructing intersection improvements at 3A Stone Oak Parkway and Evans Road and at 3B Stone Oak Parkway and Hardy Oak Boulevard. • Timeline: summer 2025-summer 2027 • Cost: $5.07 million • Funding source: 2022 General Obligation Bond 4 De Zavala Road project Project: The De Zavala Road project will add a series of improvements, including a large pipe underneath the
1604
Shavano Park
2
4
GREEN SPRING RD.
LOCKHILL SELMA RD.
6 Loop 1604 from Redland Road to Judson Road Project: Part of the Loop 1604 North Expansion Project, the Loop 1604 from Redland Road to Judson Road project aims to upgrade the transit corridor from four lanes to a 10-lane expressway. Update: The project is 21% complete. • Timeline: 2025-28 • Cost: $205 million • Funding source: state and federal funds
JONES MALTSBERGER RD.
10
WURZBACH PKWY.
281
WURZBACH PKWY.
5
SAN ANTONIO INTERNATIONAL AIRPORT
1
410
WURZBACH RD.
10
MAP NOT TO SCALE N
STONE OAK 23026 US Hwy 281 N (210) 497-1322
VINEYARD 1309 N Loop 1604 W (210) 408-8206
LEGACY 2003 N Loop 1604 E (210) 494-8600
DE ZAVALA 5219 De Zavala Rd (210) 561-0900
RECTOR 819 E Rector Dr (210) 340-2244
Powered by FlippingBook