Upcoming projects
NORTHWEST BLVD.
LAKE GEORGETOWN
130 TOLL
SERENADA DR.
1 Williams Drive Project: Construct medians with turn lanes on Williams Drive from I-35 to Serenada Drive, including a shared- use path on the north side of Williams Drive and a new waterline Update: In the design phase, with street light work anticipated to begin in early 2026
4
LAKEWAY DR.
1
35
• Timeline: 2023-27 • Cost: $18.6 million • Funding source: city of Georgetown 2 Hwy. 29 West
RIVERY BLVD.
OAK RIDGE RD.
WOLF RANCH PKWY.
Project: Construct additional travel lanes, lengthen turn lanes and improve traffic signals on Hwy. 29 from Wolf Ranch Parkway to I-35, including shared-use paths Update: In the design phase, with construction expected to begin in early 2026 • Timeline: 2023-26 • Cost: $10.1 million • Funding source: Georgetown Transportation Enhancement Corporation 3 Leander Road Project: Expand Leander Road to four lanes from Southwest Bypass to Norwood Drive Update: In the property acquisition and design phase • Timeline: 2019-26 • Cost: $32.56 million • Funding sources: city of Georgetown, grants 4 DB Wood Road Phase 2 Project: Widen the road to four lanes with a median and a shared-use path from Oak Ridge Road to the Public Safety Operations and Training Center near Williams Drive Update: Design is complete, and construction is anticipated to start in May
2
7
UNIVERSITY PARK DR.
29
SOUTHWESTERN BLVD.
5
130 TOLL
SAM HOUSTON AVE.
NORWOOD DR.
6
35
1460
3
E S T B
MAP NOT TO SCALE N
1460 Inner Loop to Sam Houston Avenue Update: In the construction phase • Timeline: 2022-26 • Cost: $12 million • Funding source: city of Georgetown 7 DB Wood Road Phase 1 Project: Add four lanes, a center turn lane and a shared- roadway with a continuous center left-turn lane and a 10-foot-wide shared-use path along one side from SE
Ongoing projects
5 Southwestern Boulevard Project: Reconstruct and expand Southwestern Boulevard to two lanes with a center turn lane from
University Park Drive to SE Inner loop Update: In the construction phase
35 • Timeline: 2020-26 • Cost: $6.58 million • Funding sources: city of Georgetown, Williamson County 6 Rockride Lane Project: Upgrade Rockride Lane to a two-lane collector
• Timeline: 2022-28 • Cost: $35 million • Funding source: city of Georgetown
use path from Hwy. 29 to Oak Ridge Road Update: Anticipated completion in May • Timeline: 2023-26 • Cost: $29.4 million • Funding source: city of Georgetown