TRANSPORTATION UPDATES
UPCOMING PROJECT
COMPILED BY SAMANTHA DOUTY
SPRINGWAY DR.
POST OAK DR.
SUNDAY HAUS LN.
Lanes are closed on Waketon Road. CATHY WILLIAMSCOMMUNITY IMPACT NEWSPAPER
N
Construction on Highland Village Road sidewalk begins The new sidewalk will connect to the existing sidewalk at the High- land Village Municipal Complex and head east along the east side of Highland Village Road, according to a city news release. The project is funded through a 2018 bond issue and was projected to cost about $883,350. Howev- er, the price increased by about $26,255 after the original contrac- tor defaulted on the project and a new contractor was hired by the city. Completion of the sidewalk will increase pedestrian safety along the road, according to the news release. Timeline: Fall 2022 Cost: $883,350 Funding source: 2018 bond
Closures continue on Waketon Road The westbound Waketon Road lane closure between Kings and Chinn Chapel roads remains in place as construction continues on the Waketon project. The Waketon project is an $8.47 million joint project with the town of Double Oak. The overall project limits are from Cross Timbers Drive in Double Oak to Parksdale Drive in Flower Mound, according to the release. The Flower Mound section of the project includes the upgrade of the existing two-lane asphalt roadway to a two-lane urban collector street section with an enclosed storm drainage system, according to the release. The project also includes the installation of a roundabout at the Waketon and Chinn Chapel intersection. The overall project is scheduled to be complete in the fall. To learn more about this and other construction projects, visit www.ower-mound.com/ constructionproject.
Step 1:
Water no more than 2 days/week
Step 2:
Water before 10am or after 6pm
landscapes, and save money on water bills, too. Visit www.WaterLessYall.com for free resources, water-saving tips and more. There are many easy, inexpensive ways to reduce water use, maintain beautiful Let’s not dance around the issue. North Texas is getting hotter, drier, and more crowded. So the more we do to save water today, the better everyone’s tomorrows will be. Let’s all do our part to conserve water this summer — and always.
ONGOING PROJECT
WHITNEY LN.
COLONIAL DR.
COLLEGE PKWY.
N
Colonial Drive project nears com- pletion The Colonial Drive Phase 2 project in Flower Mound nears its end in June. The project consists of the reconstruction of Colonial from Whitney Lane to Homestead Drive. It includes sidewalk improvements, according to the town. Construc- tion started in June 2021. Paving work continues. Timeline: June 2022 Cost: $2.49 million Funding sources: dedicated sales tax, wastewater, stormwater
Timeline: September 2022 Project cost: $8.47 million
Funding sources: interlocal funds, es- crow, tax increment reinvestment zone, tax debt
CHINN CHAPEL RD.
DIXONRD.
CHAPEL HILL DR.
WAKETON RD.
ALL INFORMATION ON THIS PAGE WAS UPDATED AS OF JUNE 3. NEWS OR QUESTIONS ABOUT THESE OR OTHER LOCAL TRANSPORTATION PROJECTS? EMAIL US AT LFHNEWSCOMMUNITYIMPACT.COM.