Transportation
BY LIZZY SPANGLER
Upcoming projects
Conroe
1 Spur 149 overlay Project: A hot mix asphalt overlay project will take place along Spur 149 between FM 1488 and FM 149. Update: This project was anticipated to start Sept. 15, according to a Sept. 11 media update from the Texas Department of Transportation. • Timeline: September 2025-fourth quarter 2025 • Cost: $1.1 million • Funding sources: federal, state funds
45
149
249 TOLL
MOSTYN DR.
4
1774
3
1488
1
2
242
2978
Magnolia
Ongoing projects
The Woodlands
2 FM 1488 widening west of Magnolia Project: Between the Waller County line and FM 1774 west of Magnolia, FM 1488 is being widened from two to four lanes with a continuous left-turn lane. Update: This project is 98% completed, according to a Sept. 11 media update from TxDOT. • Timeline: November 2020-third quarter 2025 • Cost: $35.35 million • Funding source: state funds 3 FM 1488 widening through Magnolia Project: FM 1488 is being widened from two to four
N
MAP NOT TO SCALE
4 FM 1488 median project Project: The project will build a median from Mostyn Drive to I-45. Update: The project is 80% complete, as of the most recent update available from TxDOT. • Timeline: first quarter 2023-second quarter 2026 • Cost: $10.96 million • Funding sources: federal, state funds
lanes with a continuous left-turn lane in Magnolia between FM 1774 and west of FM 149. Update: According to a Sept. 11 media update from TxDOT, this project is 60% completed. • Timeline: June 2022-third quarter 2027 • Cost: $48.3 million • Funding source: state funds
Davina Hosick | Senior Commercial Relationship Manager
Our North Houston commercial bankers are focused on the success of your business.
Find us in Vintage Park
MEMBER FDIC home24bank.com | 281.276.1846
15
TOMBALL - MAGNOLIA EDITION
Powered by FlippingBook