Tomball - Magnolia Edition | September 2025

Transportation

BY LIZZY SPANGLER

Upcoming projects

Conroe

1 Spur 149 overlay Project: A hot mix asphalt overlay project will take place along Spur 149 between FM 1488 and FM 149. Update: This project was anticipated to start Sept. 15, according to a Sept. 11 media update from the Texas Department of Transportation. • Timeline: September 2025-fourth quarter 2025 • Cost: $1.1 million • Funding sources: federal, state funds

45

149

249 TOLL

MOSTYN DR.

4

1774

3

1488

1

2

242

2978

Magnolia

Ongoing projects

The Woodlands

2 FM 1488 widening west of Magnolia Project: Between the Waller County line and FM 1774 west of Magnolia, FM 1488 is being widened from two to four lanes with a continuous left-turn lane. Update: This project is 98% completed, according to a Sept. 11 media update from TxDOT. • Timeline: November 2020-third quarter 2025 • Cost: $35.35 million • Funding source: state funds 3 FM 1488 widening through Magnolia Project: FM 1488 is being widened from two to four

N

MAP NOT TO SCALE

4 FM 1488 median project Project: The project will build a median from Mostyn Drive to I-45. Update: The project is 80% complete, as of the most recent update available from TxDOT. • Timeline: first quarter 2023-second quarter 2026 • Cost: $10.96 million • Funding sources: federal, state funds

lanes with a continuous left-turn lane in Magnolia between FM 1774 and west of FM 149. Update: According to a Sept. 11 media update from TxDOT, this project is 60% completed. • Timeline: June 2022-third quarter 2027 • Cost: $48.3 million • Funding source: state funds

Davina Hosick | Senior Commercial Relationship Manager

Our North Houston commercial bankers are focused on the success of your business.

Find us in Vintage Park

MEMBER FDIC home24bank.com | 281.276.1846

15

TOMBALL - MAGNOLIA EDITION

Powered by