Frisco | October 2025

BY SAMANTHA DOUTY

Update: The project is in the design phase. • Timeline: fall 2025-mid 2026 • Cost: $300,000 • Funding source: city of Frisco 4 Lebanon Road traffic light Project: A new traffic light is being installed at the intersection of Lebanon Road and 4th Army Drive. Update: The light poles have been installed. • Timeline: end of 2024 to fall 2025 • Cost: $250,000 • Funding source: city of Frisco 5 Lebanon Road widening Project: Lebanon Road will be widened from a four-lane divided roadway to a six-lane divided roadway from FM 423 to Todd Drive. Update: The design phase of the project wrapped in mid-2025 and has moved to the construction phase. • Timeline: fall 2025-mid 2027 • Cost: $22.98 million • Funding source: city of Frisco, external funding 6 Panther Creek Parkway extension Project: Panther Creek Parkway is being constructed from Dallas North Tollway to Preston Road. Update: The project is under construction.

• Timeline: 2024-end of 2025 • Cost: $56.4 million • Funding source: city of Frisco, Collin County 7 Hillcrest Road construction

Ongoing project

Project: Hillcrest Road is expanded from two lanes to a four-lane divided roadway from Panther Creek Parkway to PGA Parkway. Update: Crews will soon begin paving work along with installing storm drains and street lights. • Timeline: 2024-end of 2025 • Cost: $5.99 million • Funding source: city of Frisco

Completed projects

9 Main Street construction Project: Main Street from BNSF railroad to North County Road and Fourth Street from Main Street to Elm Street is being reconstructed. The project will increase sidewalk widths, improve intersections and construct a pedestrian plaza. Update: Traffic patterns continue to shift as construction progresses in the Rail District. It is on track for its 2026 completion. • Timeline: early 2024-early 2026 • Cost: $20.54 million • Funding source: city of Frisco

8 Stonebrook Parkway traffic light installation Project: A new traffic light has been installed on Stonebrook Parkway at the Walmart exit just east of FM 423. Update: The project is completed. • Timeline: end of 2024-October 2025 • Cost: $250,000 • Funding source: city of Frisco

Auto Accidents | Commercial Accidents | Wrongful Death | Personal Injury

For others, it’s just a Business... For us, it’s personal

Jeremy W. McKey

Certifications: Board Certified Personal Injury Trial Law Texas Board Of Legal Specialization Licensed: Supreme Court of Texas United States District Court Southern/Eastern/Northern District of Texas

5899 Preston Rd. STE. 203, Frisco | mckeylawfirm.com | 214-855-8788

25

FRISCO EDITION

Powered by