GATEWOOD RESERVE LN.

Timeline: March 2020-summer 2022 Cost: $92 million Funding source: HCTRA 2 Gosling Road widening Work on a new bridge is underway over Spring Creek as part of a project to widen Gosling Road to four lanes between Creekside Forest Drive and Gatewood Reserve Lane. The project began as a joint e‰ort between Montgomery County Precinct 3 and Harris County Precinct 4; however, due to redistricting, Gosling Road is now in Harris County Precinct 3, which will complete the project. The project will create two 12-foot lanes in each direction as well as the two addi- tional lanes for a 1,817-foot bridge over Spring Creek. Northbound Gosling Road will be restriped at the intersection with Creekside Forest Drive for two lanes and a left-turn lane. Timeline: December 2021-early 2023 Cost: $8.2 million Funding sources: Harris County Precinct 4, Montgomery County Precinct 3 UPCOMING PROJECTS 3 FM 1960 widening The Texas Department of Transportation is

expecting to seek bids in June for a project that will widen FM 1960 from six to eight lanes with a raised median between Hwy. 249 and Cutten Road. The project will also replace the roadway’s existing pavement and tra¢c signals and install a continuous sidewalk and storm sewers along the corridor. Pending the completion of several private utility relocations required for the project, TxDOT aims to begin construction in August. Timeline: August 2022-December 2024 Cost: $20 million Funding sources: 80% federal, 20% state 4 FM 2920 improvements TxDOT is designing a project to add raised medians and right-turn lanes along FM 2920 between I-45 in Spring and North Willow Street in Tomball. TxDOT sought construction bids in August, and the proj- ect was awarded to MBN Enterprises LLC. As of press time March 16, a construction timeline for the project had not yet been determined; however, the project is expected to take 16 months to complete once construction begins. Timeline: TBD Cost: $3.6 million Funding sources: 80% federal, 20% state

N. WILLOW ST.

SPRING CREEK

2920

2

4

249

CREEKSIDE FOREST DR.

1

99 TOLL

45

1960

3

MAP NOT TO SCALE N

ONGOING PROJECTS 1 Grand Parkway direct connectors The Harris County Toll Road Authority is nishing columns, beams and decks for its project to add four direct connec- tors between Hwy. 249 and the Grand

Parkway in Tomball. Once completed, northbound drivers on the tolled lanes of Hwy. 249 will be able to enter eastbound and westbound Grand Parkway lanes, and those traveling east or west on the Grand Parkway will have direct access to southbound Hwy. 249 tolled lanes.

ALL INFORMATION ON THIS PAGE WAS UPDATED AS OF MARCH 9. NEWS OR QUESTIONS ABOUT THESE OR OTHER LOCAL TRANSPORTATION PROJECTS? EMAIL US AT SKLNEWSœCOMMUNITYIMPACT.COM.