Cedar Park - Far Northwest Austin Edition | May 2023

TRANSPORTATION UPDATES Changes ahead for 8 Anderson Mill Road intersections

ONGOING PROJECTS

45 TOLL

BY BRITTANY ANDERSON

Starting in June, once all of the above roads along the northbound side of Anderson Mill Road are com- plete, crews will then work on five intersections along the southbound side in the following order: • Zeppelin Drive • Grand Falls Drive • Passionflower Pass • Quiet Moon Trail • Cypress Creek Road While Phase 1 reconstructed the road between Gaspar Bend and Whitestone Boulevard, Phase 2 of the project includes widening the remaining two-lane sections on the road to four lanes between Cypress Creek and Whitestone. Additional work for Phase 2 includes a new sidewalk, new curb and gutter, signal modifications, signage, and drainage improve- ments, as previously reported by Community Impact . Phase 2 of the project began in January, and the project is on track to be completed in early 2024.

KEEPING UP WITH CLOSURES

MOPAC

Traffic pattern shifts are next on the scope of work for the $7.7 million Anderson Mill Road widening project, funded through the 2022 Cedar Park voter-approved bond. Work for part of Phase 2 of the project began on Drifting Leaf Drive on May 1, shifting traffic to one side of the road to give contractors room to install new curbs, ramps and drainage facilities. Five northbound intersections will be worked on in the following order, and work will take about a week to complete: • Drifting Leaf Drive • Grand Falls Drive • Shady Creek Trail • Rhapsody Ridge Drive • Zeppelin Drive (once school is out for summer break) Shady Creek and Rhapsody will have flaggers stationed to help guide traffic, while the other roads are wide enough to maintain two-way traffic throughout construction.

620

183

35

Work on part of Anderson Mill Road’s Phase 2 will begin at the northbound intersection of Drifting Leaf Drive up through Zeppelin Drive in May and move southbound down to Cypress Creek Road in June.

N

ALL INFORMATION ON THIS PAGE WAS UPDATED AS OF MAY 3. NEWS OR QUESTIONS ABOUT THESE OR OTHER LOCAL TRANSPORTATION PROJECTS? EMAIL US AT CPFNEWS@COMMUNITYIMPACT.COM. Funding sources: Central Texas Regional Mobility Authority, Texas Department of Transportation 183 North widening The 183 North Mobility Project—a $612 million transportation project meant to alleviate congestion and improve emergency response times—is on track for a 2026 completion date. Over the next several weeks through the summer, crews will focus on earth- work, storm sewer drainage, bridge work, retaining wall work, paving, electrical and franchise utility adjust- ments, and pavement grinding. Timeline: January 2022-26 Cost: $612 million

Northbound closures in May Southbound closures in June

RHAPSODY RIDGE DR.

SHADY CREEK TRL. GRAND FALLS DR.

PASSIONFLOWER PASS

DRIFTING LEAF DR.

QUIET MOON TRL.

N

SOURCE: CITY OF CEDAR PARK/COMMUNITY IMPACT

GET IN THE ACT! Broadway Kids • Acting • Improv • Musical Theatre Weekly Summer Camps in Cedar Park ZACH North Campus | May 30-August 10 14010 North Highway 183, Suite 540

Register at zachtheatre.org/education

Summer Camp Presenting Sponsor

14

COMMUNITYIMPACT.COM

Powered by