BY CONNOR PITTMAN
Project 3
Looking forward
Highland Village Road asphalt overlays Phase 3
2025
OAK ST.
CEDAR DR.
Mid-2025: Construction on Lakeside Parkway begins Late 2025: Work on Highland Village Road, Highland Shores Boulevard starts
Highland Village
REDWOOD DR.
HIGHLAND SHORES BLVD.
FERNDALE DR.
SELLMEYER LN.
MERRIMAN DR.
2026
HIGHLAND VILLAGE RD.
SELLMEYER LN.
Early to mid-2026: Lakeside Parkway construction expected to finish
N. GARDEN RIDGE BLVD.
GAYLE LN.
CANYON CREEK DR.
Lewisville
Mid-2026: Highland Village Road construction completion
35E
MEDINA DR.
JUSTIN RD.
JUSTIN RD.
N
2027
SOURCE: CITY OF HIGHLAND VILLAGE/COMMUNITY IMPACT
did from the Highland Shores intersection north to the I-35 frontage road,” Kriston said. For neighborhood streets, such as Oak Street and Gale Lane, the city will conduct various repairs and apply a fresh layer of asphalt to improve driving con- ditions, which should prevent further reconstruction aside from planned maintenance, Kriston said.
In some places, Highland Village Road has reached total concrete failure, Kriston said. The project aims to extend the road’s lifespan by fixing drainage issues, adding 5 to 6 feet for a wider shoulder, adding a left-turn lane at the Canyon Creek Drive intersec- tion and improving mobility for golf carts in the area. “We’re going to mirror the reconstruction that we
Late 2027: Highland Shores Boulevard construction ends
SOURCE: CITY OF HIGHLAND VILLAGE, TOWN OF FLOWER MOUND/ COMMUNITY IMPACT
NORTH DFW PREMIER WINDOW & DOOR REPLACEMENT EXPERTS
TRANSFORM YOUR HOME
FAMILY-OWNED & OPERATED
FREE ESTIMATE 469-436-9106 SPRING SPECIAL 10% OFF windows and installation* *With the purchase of 4 or more windows
Before
SCAN HERE
Serving Flower Mound, Highland Village, Lewisville & surrounding communities
After
13
FLOWER MOUND - HIGHLAND VILLAGE - ARGYLE EDITION
Powered by FlippingBook