Ongoing projects

E. MCCART ST.

380

288

EMERYST.

5

1

WINDSOR DR.

C O R D E L L S T .

PANHANDLE ST.

3

35

77

RINEY RD.

EGANST.

N. ELM ST.

6

4

SCRIPTURE ST.

W. UNIVERSITY BLVD.

380

OAKST.

PONDER ST.

156 Update: Contractors installed storm drain lines and curb inlets between Riney Road and North Elm Street. • Timeline: The sixth phase is expected to be complete in 2027. 1 Bonnie Brae Street Project: The street is being reconstructed to widen three miles from Scripture Street to Loop 288 and build a continuous four-lane divided road.

288

PANHANDLE ST.

WESTERN BLVD.

W. HICKORY ST.

2

SHADY OAKS RD.

CARROLL BLVD.

35E

CHESTNUT ST.

AIRPORT RD.

35W

Denton

MAP NOT TO SCALE N

• Cost: $38 million for sixth phase • Funding source: city of Denton

COLORADO BLVD.

and installing concrete. There are also curb and gutter improvements, which will be followed by driveway updates and miscellaneous concrete work. • Timeline: completion in late May • Cost: $826,019.93 from 2019 bond • Funding source: city of Denton 4 Ponder Street Project: The work includes utility installations, pavement replacement and storm drainage updates. Update: Crews are pouring concrete and backlling with sod, installing multiple inlets for storm drainage and the curb installation along multiple sections of the street. • Timeline: scheduled completion in late March • Cost: $2,235,149.05 from 2019 bond • Funding source: city of Denton 5 Fulton Street Project: A full road reconstruction is planned and 2449 VINTAGE BLVD.

includes new water and sewer lines. Update: Workers will begin installing the curbs and gutters, followed by updated driveways and miscellaneous concrete work. • Timeline: scheduled completion in late March

Ongoing projects

2 North Bernard Street Project: Work includes completely reconstructing the street, drainage improvements and utility updates. Update: Crews with the city have set up trac control and started installing the water main. • Timeline: late July completion • Cost: $7,240,901.67 from 2019 bond • Funding source: city of Denton 3 Panhandle Street Project: The updates include repaving the street, drainage improvements and utility improvements. Update: Crews are adjusting the rst layer of asphalt

• Cost: $179,951.03 from 2019 bond • Funding source: city of Denton

Completed projects

6 Egan Street Project: The work included utility installations, pavement replacement and storm drainage updates. Update: Crews installed the top layer of asphalt and removed trac control signs along the road. • Timeline: road reopened in mid-February • Cost: $735,703.02 from 2019 bond • Funding source: city of Denton