Transportation
BY ADAM DOE
Ongoing projects
E. MCCART ST.
380
288
EMERYST.
5
1
WINDSOR DR.
C O R D E L L S T .
PANHANDLE ST.
3
35
77
RINEY RD.
EGANST.
N. ELM ST.
6
4
SCRIPTURE ST.
W. UNIVERSITY BLVD.
380
OAKST.
PONDER ST.
156 Update: Contractors installed storm drain lines and curb inlets between Riney Road and North Elm Street. • Timeline: The sixth phase is expected to be complete in 2027. 1 Bonnie Brae Street Project: The street is being reconstructed to widen three miles from Scripture Street to Loop 288 and build a continuous four-lane divided road.
288
PANHANDLE ST.
WESTERN BLVD.
W. HICKORY ST.
2
SHADY OAKS RD.
CARROLL BLVD.
35E
CHESTNUT ST.
AIRPORT RD.
35W
Denton
MAP NOT TO SCALE N
• Cost: $38 million for sixth phase • Funding source: city of Denton
COLORADO BLVD.
and installing concrete. There are also curb and gutter improvements, which will be followed by driveway updates and miscellaneous concrete work. • Timeline: completion in late May • Cost: $826,019.93 from 2019 bond • Funding source: city of Denton 4 Ponder Street Project: The work includes utility installations, pavement replacement and storm drainage updates. Update: Crews are pouring concrete and backlling with sod, installing multiple inlets for storm drainage and the curb installation along multiple sections of the street. • Timeline: scheduled completion in late March • Cost: $2,235,149.05 from 2019 bond • Funding source: city of Denton 5 Fulton Street Project: A full road reconstruction is planned and 2449 VINTAGE BLVD.
includes new water and sewer lines. Update: Workers will begin installing the curbs and gutters, followed by updated driveways and miscellaneous concrete work. • Timeline: scheduled completion in late March
Ongoing projects
2 North Bernard Street Project: Work includes completely reconstructing the street, drainage improvements and utility updates. Update: Crews with the city have set up trac control and started installing the water main. • Timeline: late July completion • Cost: $7,240,901.67 from 2019 bond • Funding source: city of Denton 3 Panhandle Street Project: The updates include repaving the street, drainage improvements and utility improvements. Update: Crews are adjusting the rst layer of asphalt
• Cost: $179,951.03 from 2019 bond • Funding source: city of Denton
Completed projects
6 Egan Street Project: The work included utility installations, pavement replacement and storm drainage updates. Update: Crews installed the top layer of asphalt and removed trac control signs along the road. • Timeline: road reopened in mid-February • Cost: $735,703.02 from 2019 bond • Funding source: city of Denton
35E
35W
156
Advertise in the Voter Guide
ADS@COMMUNITYIMPACT.COM PRINT + DIGITAL PACKAGES | DIRECT MAIL
11
DENTON EDITION
Powered by FlippingBook