138
Transportation
BY MANUEL HOLGUIN JR.
Upcoming project
45 TOLL
Hutto
130 TOLL
INNOVATION BLVD.
6
2
MOORLYNCH AVE.
130 TOLL
PFLUGER FARM LN.
LIMMER LOOP
TOWN CENTER DR.
PARKWAY DR.
1
Pflugerville
35
685
3
HELIOS WAY
130 TOLL
1 Kelly Lane Phase 3 Project: The city will reconstruct about 1.3 miles of Kelly Lane between Moorlynch Avenue and Weiss Lane, expanding the roadway from a two-lane road into a four-lane divided arterial, with four roundabout intersections. Update: Project to go out to bid this spring • Timeline: Completion planned for early 2030 • Cost: $31.5 million • Funding source: city bond funds
IMPACT WAY
CAMERON RD.
5
4
MAP NOT TO SCALE
N TM; © 2026 COMMUNITY IMPACT CO. ALL RIGHTS RESERVED.
Update: Construction is underway on the new Helios Way right-in and right-out driveway and the final phase of Impact Way. • Timeline: Completion expected in mid-March • Cost: $5.8 million • Funding source: Pflugerville Community Development Corporation Type B sales tax Hutto Upcoming projects 6 Traffic Signal - Innovation at Limmer Loop Project: A traffic signal will be installed at Innovation Boulevard and Limmer Loop. Update: This project is nearing completion. Oncor is finalizing the remaining electrical work needed to activate the flashing lights. After all work is finished, the signal will operate in flashing mode for a short period before transitioning into a fully functioning traffic light. • Timeline: An exact timeline is TBD; Residents will be notified when construction begins • Cost: $2.23 million • Funding source: Capital Projects fund
drainage, sidewalks and streetlights. Update: In its final design and bidding preparation phase. • Timeline: Expected to go out to bid in May • Cost: $3.4 million • Funding source: Roadway impact fees, city bonds, community development block grant
Pflugerville Upcoming projects
Ongoing projects
4 East Pflugerville Parkway realignment Project: A 1-mile extension of East Pflugerville Parkway, from Weiss Lane to Jesse Bohls Drive, will include a four-lane roadway with a raised center median. Update: Construction began in mid-January • Timeline: Final completion expected in May 2027 • Cost: $10.7 million • Funding source: City bonds, roadway impact fees 5 Helios Way Project: The street will be extended and upgraded to improve access to the SH 130 frontage road and support industrial development.
2 Pfluger Farm Lane North Project: A section of Pfluger Farm Lane will be widened into a three-lane road. Update: Design is about 95% complete • Timeline: Expected to go out to bid in September • Cost: $6.5 million • Funding source: city bond funds, roadway impact fees 3 Parkway Drive reconstruction Project: Parkway Drive will be reconstructed into an urban road section with pavement, curb, gutter