INFRASTRUCTURE Construction of Heritage Trail West project expected to resume in 2023
TRAIL TIEIN The Heritage Trail West project will connect to the countywide Brushy Creek Regional Trail once complete and provide additional amenities for its users.
10-foot-wide paved trails spanning from Bathing Beach at Chisholm Trail Road to Mays Street Interpretive historical markers detailing the history of Round Rock as a timeline Improvements made to Bathing Beach, Chisholm Trail Crossing and Memorial parks
BY BROOKE SJOBERG
The city originally awarded the $7.3 million contract to Ritter, Botkin Prime Construction Co. in June 2020, and construction began on the trail segment in January 2021. At the Aug. 25 council meeting, Atkins said the rebidding guidelines will require the new contractor to take over liability for the trail upgrade project, which he said is already about 20%-25% complete. Hal Associates Inc. is engaged in an engineering contract to survey the existing project and determine its status, Atkins said during an Aug. 23 preparation meeting. “If we thought we really could just say, ‘Hey, here’s a lot of money. Go do this. Just give us a project,’ and walk away from it, we would do that,” Atkins said. “But I think with just the way that prices have gone, we’ve got to be able to look at the pricing that we’re going to have.”
Round Rock ocials took the rst step in the process to rebid the Heritage Trail West project following bankruptcy of the original contractor. The Heritage Trail West project is funded by a 2013 bond and will connect the approximately 1-mile span between Chisholm Trail Road and North Mays Street along Brushy Creek. City Council approved a resolution to rebid the project through a sealed proposal at an Aug. 25 meeting. Parks and Recreation Director Rick Atkins said the sealed proposal method will allow the city to select its next contractor for the project based on experience, nancials and com- pany history, among other factors. In February, Atkins told City Council that the original contractor, Pugerville-based Ritter, Botkin Prime Construction Co., led for bankruptcy in late 2021.
BROOKE SJOBERGCOMMUNITY IMPACT
BRUSHY CREEK REGIONAL TRAIL
Heritage Trail West project
CHISHOLM TRAIL RD.
620
35
N
SOURCE: CITY OF ROUND ROCKCOMMUNITY IMPACT
Atkins said the goal is to rebid the project by the end of the year with work starting after Jan. 1. In September 2021, the city contracted with artist Antonio Munoz
to create up to 10 bronze statues to complement the trail improvement project. City estimates state the statues will come in phases and be complete by 2026.
SEPT 29 - OCT 22
ON TWO OR MORE BOTTLES OF SOURCED WINE *
IN-STORE & ONLINE
SCAN TO SHOP OUR CURRENT SPECIALS
TWINLIQUORS.COM
*Twin Sourced Wine Sale runs 9/29/2022-10/22/2022. Valid on featured products. Sale items can be shopped in-store and online at www.twinliquors.com. Selection varies by store. Items and prices subject to change without notice. No further discount on Sale Items, Final Few, or Closeouts. Some exclusions apply. Please drink responsibly.
ALL YOUR HOME FINANCIAL NEEDS UNDER ONE ROOF Apply at VelocityLoans.com or call 512.469.7177. Purchase • Refinance • Jumbo Loans • Home Equity
17
ROUND ROCK EDITION • OCTOBER 2022
Powered by FlippingBook