Grapevine - Colleyville - Southlake | April 2025

Colleyville to invest $50 million in roads From the cover

The projects

Key:

Construction

Design

In the works

11

MONTICELLO PKWY.

1 Jackson Road Bridge Widen travel lanes to 12 feet, add 4-foot wide shoulders and 5-foot wide sidewalks Timeline: estimated completion summer 2025 Total cost: $1.75 million Funding source: Texas Department of Transportation 2 Tinker Road Add new storm sewer system; replace water and wastewater lines; add new sidewalk on the north side; curb ramps; repave road Timeline: estimated completion in October Total cost: $2.09 million Funding source: city of Colleyville 3 Green Ribbon Projects Adding trees and shrubs along these highway corridors: A SH 121 B FM 3029 C Hwy. 26 Timeline: estimated start fall 2025, estimated completion by end of year Total cost: $1.5 million Funding source: TxDOT, city of Colleyville 4 Roberts Road Road rehabilitation from Glade Road to Grapevine Timeline: estimated start late 2025 Total cost: $1.4 million Funding source: city of Colleyville 5 Cheek-Sparger Road/Bedford Road Adding roundabout at intersection of Cheek-Sparger Road and Bedford Road Timeline: estimated start early 2026 Total cost: $2.35 million Funding source: city of Colleyville 6 Heritage Avenue Bridge Reconstruction of bridge and addition of right-turn lane at Heritage Avenue and Cheek-Sparger Road Timeline: planned for 2026 Total cost: $750,000 Funding source: Tarrant County 7 John McCain Bridge Design and replacement of the bridge west of Monticello Parkway over White Chapel Creek Timeline: end of 2025 estimated start, estimated completion summer 2026 Total cost: $525,312 Funding source: TxDOT, city of Colleyville

DAVIS BLVD.

3C

Grapevine

JOHN MCCAIN RD.

7

MCDONWELL SCHOOL RD.

2

3B

13

TINKER RD.

HERITAGE AVE.

121

Colleyville

3029

HALL - JOHNSON RD.

BIRCH AVE.

ROBERTS RD.

26

12

3A

4

W. GLADE RD.

MARTIN PKWY.

1

GUADALUPE DR.

8

JACKSON RD.

9

CHEEK-SPARGER RD.

6

5

10

N MAP NOT TO SCALE

8 Heritage Avenue Reconstruction from Cheek-Sparger Road to Guadalupe Drive Timeline: planned for 2026 Total cost: $2.35 million Funding source: federal grants 9 Cheek-Sparger Road Design and reconstruction from Heritage Avenue to Bedford Road, including intersection at Martin Parkway. Installation of storm sewer, water lines, trails and sidewalks Timeline: estimated start 2028 Total cost: $35.64 million Funding source: state funding, North Central Texas Council of Governments, Tarrant County, city of Colleyville 10 Cheek-Sparger Road/Martin Parkway Addition of traffic control measures at intersection Timeline: design to begin 2026

Total cost: Estimated $1.5 million Funding source: TBD 11 Monticello Parkway* Road resurfacing and replacing main water line Timeline: planned for 2028

Total cost: $200,000 Funding source: TBD

12 West Glade Road* Reconstructing Glade Road from Bransford West to Colleyville city limits Timeline: design to begin 2029

Total cost: $250,000 Funding source: TBD

13 McDonwell School Road* Addition of turn lanes at key intersections Timeline: design to begin 2029

Total cost: $250,000 Funding source: TBD

SOURCE: CITY OF COLLEYVILLE/COMMUNITY IMPACT

*THE SCOPE AND EXACT LOCATIONS OF THESE PROJECTS WILL BE DETERMINED AT A LATER DATE