Pflugerville - Hutto Edition | September 2025

Transportation

BY GRACIE WARHURST

101

395

GRANT AVE.

Completed projects

EXCHANGE BLVD.

3

8

LINCOLN AVE.

CALDWELLS LN.

LIMMER LOOP

6

9

7

79

Hutto

132

TAYLOR ST.

130 TOLL

1660

RED BUD LN.

E. WILCO HIGHWAY

404

OOLRD.

3349

137

45 TOLL

1 Kelly Lane Phase 2 Project: Widening Kelly Lane from 2 to 4 lanes from Falcon Pointe Drive to east of Moorlynch Avenue, including a roundabout at Vilamoura Street. Update: Final construction activities will continue through September. • Timeline: 2019-2025 • Cost: $27.6 million for total project • Funding source: CO 2020, GO 2020A and roadway impact fees

COLORADO SAND DR.

GREENLAWN BLVD.

VILAMOURA ST.

MOORLYNCH AVE.

KELLY LN.

COPPER MINE DR.

2

GRAND AVE. PKWY.

5

1

WY.

FALCON POINTE BLVD.

VISION DR.

LONE STAR RANCH BLVD.

35

4

685

Pugerville

MANGAN WAY

N

MAP NOT TO SCALE

DESSAU RD.

Pugerville

approximately six months. • Timeline: 2023-2025 • Cost: $5.9 million • Funding source: 2023 CO Bond, 2020 GO Bond

improvements at the intersection of FM 1660 South and Hwy. 79, and the intersection of FM 1660 South and Front Street. Update: Now moving forward with TxDOT and Union Pacic Railroad coordination. TxDOT design of the signal at Front Street is now complete. • Timeline: 2023-2027 • Cost: $4,453,574 • Funding Source: 2022 GO bond

Upcoming projects

2 Kelly Lane Phase 3 Project: The city will expand the road to a four-lane conguration with a center median from Moorlynch Avenue to Weiss Lane. Update: The project has entered the nal phases of design and construction will begin with utility relocation. • Timeline: 2020-2028 • Cost: $28.7 million • Funding source: 2022, 2023 GO bonds, impact fees

Completed projects

5 Colorado Sand Drive from Copper Mine to Lone Star Ranch Blvd Project: Construction of a half mile, 4-lane paved roadway to ll the gap on Colorado Sand Drive between Copper Mine Drive and Lone Star Ranch Boulevard, including a roundabout. Update: Construction was completed in September. • Timeline: 2019-2025 • Cost: $9.9 million • Funding source: CO 2023, GO 2020 and roadway impact fees Hutto

Ongoing projects

8 FM 1660 at Limmer Loop Project: Construction of turn lanes and signal improvements at the intersection of FM 1660 North and Limmer Loop. Update: The road is under construction with an estimated completion of late 2025. Final paving and striping is expected soon. • Timeline: 2023-2025 • Cost: $7,884,001 • Funding Source: 2022 GO bond

Ongoing projects

3 Historic Colored Addition Subdivision Streets Project: The project includes full reconstruction of each of the existing subdivision roadways—Lincoln Avenue, Taylor Street, Caldwells Lane and Russell Street—and new construction of Grant Avenue. • Update: The irst phase of construction is ongoing. • Timeline: 2019-2027 • Cost: $11.2 million • Funding source: General Fund, Utility Fund, 2020 Transportation Bond Program 4 Street Reconstruction Package 1B Project: The neighborhood street reconstruction project will rehabilitate 18 neighborhood streets in the Saxony and Willow Creek Section One subdivisions. Update: Construction started in July and will last

Upcoming projects

Completed projects

6 Exchange Boulevard reconstruction Project: Improvements to Exchange Boulevard at the intersection with Live Oak. Update: Design is 90% complete. Work continues as right-of-way details are nalized. • Timeline: 2025-2026 • Cost: $4.4 million • Funding Source: 2022 GO bond 7 FM 1660 South at Hwy. 79 Project: Construction of the turn lanes and signal

9 East Wilco Highway Segment 3 Project: Williamson County widened FM 3349 and CR 101 into a four-lane divided roadway with bridges over Hwy. 79 and the Union Pacic Railroad. Update: Construction on the roadway was completed in June. • Timeline: June 21 • Cost: $95 million • Funding Source: Texas Department of Transportation

13