Transportation
BY GRACIE WARHURST
101
395
GRANT AVE.
Completed projects
EXCHANGE BLVD.
3
8
LINCOLN AVE.
CALDWELLS LN.
LIMMER LOOP
6
9
7
79
Hutto
132
TAYLOR ST.
130 TOLL
1660
RED BUD LN.
E. WILCO HIGHWAY
404
OOLRD.
3349
137
45 TOLL
1 Kelly Lane Phase 2 Project: Widening Kelly Lane from 2 to 4 lanes from Falcon Pointe Drive to east of Moorlynch Avenue, including a roundabout at Vilamoura Street. Update: Final construction activities will continue through September. • Timeline: 2019-2025 • Cost: $27.6 million for total project • Funding source: CO 2020, GO 2020A and roadway impact fees
COLORADO SAND DR.
GREENLAWN BLVD.
VILAMOURA ST.
MOORLYNCH AVE.
KELLY LN.
COPPER MINE DR.
2
GRAND AVE. PKWY.
5
1
WY.
FALCON POINTE BLVD.
VISION DR.
LONE STAR RANCH BLVD.
35
4
685
Pugerville
MANGAN WAY
N
MAP NOT TO SCALE
DESSAU RD.
Pugerville
approximately six months. • Timeline: 2023-2025 • Cost: $5.9 million • Funding source: 2023 CO Bond, 2020 GO Bond
improvements at the intersection of FM 1660 South and Hwy. 79, and the intersection of FM 1660 South and Front Street. Update: Now moving forward with TxDOT and Union Pacic Railroad coordination. TxDOT design of the signal at Front Street is now complete. • Timeline: 2023-2027 • Cost: $4,453,574 • Funding Source: 2022 GO bond
Upcoming projects
2 Kelly Lane Phase 3 Project: The city will expand the road to a four-lane conguration with a center median from Moorlynch Avenue to Weiss Lane. Update: The project has entered the nal phases of design and construction will begin with utility relocation. • Timeline: 2020-2028 • Cost: $28.7 million • Funding source: 2022, 2023 GO bonds, impact fees
Completed projects
5 Colorado Sand Drive from Copper Mine to Lone Star Ranch Blvd Project: Construction of a half mile, 4-lane paved roadway to ll the gap on Colorado Sand Drive between Copper Mine Drive and Lone Star Ranch Boulevard, including a roundabout. Update: Construction was completed in September. • Timeline: 2019-2025 • Cost: $9.9 million • Funding source: CO 2023, GO 2020 and roadway impact fees Hutto
Ongoing projects
8 FM 1660 at Limmer Loop Project: Construction of turn lanes and signal improvements at the intersection of FM 1660 North and Limmer Loop. Update: The road is under construction with an estimated completion of late 2025. Final paving and striping is expected soon. • Timeline: 2023-2025 • Cost: $7,884,001 • Funding Source: 2022 GO bond
Ongoing projects
3 Historic Colored Addition Subdivision Streets Project: The project includes full reconstruction of each of the existing subdivision roadways—Lincoln Avenue, Taylor Street, Caldwells Lane and Russell Street—and new construction of Grant Avenue. • Update: The irst phase of construction is ongoing. • Timeline: 2019-2027 • Cost: $11.2 million • Funding source: General Fund, Utility Fund, 2020 Transportation Bond Program 4 Street Reconstruction Package 1B Project: The neighborhood street reconstruction project will rehabilitate 18 neighborhood streets in the Saxony and Willow Creek Section One subdivisions. Update: Construction started in July and will last
Upcoming projects
Completed projects
6 Exchange Boulevard reconstruction Project: Improvements to Exchange Boulevard at the intersection with Live Oak. Update: Design is 90% complete. Work continues as right-of-way details are nalized. • Timeline: 2025-2026 • Cost: $4.4 million • Funding Source: 2022 GO bond 7 FM 1660 South at Hwy. 79 Project: Construction of the turn lanes and signal
9 East Wilco Highway Segment 3 Project: Williamson County widened FM 3349 and CR 101 into a four-lane divided roadway with bridges over Hwy. 79 and the Union Pacic Railroad. Update: Construction on the roadway was completed in June. • Timeline: June 21 • Cost: $95 million • Funding Source: Texas Department of Transportation