DEVELOPMENT UPDATES

Projects underway in the New Braunfels area

COMPILED BY SIERRA MARTIN & ERIC WEILBACHER

ERIC WEILBACHERCOMMUNITY IMPACT

ERIC WEILBACHERCOMMUNITY IMPACT

ERIC WEILBACHERCOMMUNITY IMPACT

VILLAS AT WATERWHEEL Villas at Waterwheel condominiums broke ground earlier this year and are slated to open to new owners in December. The three-story building oers 54 two- bedroom, two-bathroom units on the Guadalupe River near Schlitterbahn, the Comal County Fairgrounds and the main branch of the New Braunfels Public Library. The resort-styled condos also feature two pools, access to the Guadalupe River and more. Space: 54 units Timeline: opens December 2022

MODERNO LUXURY APARTMENT HOMES Koontz Corp. broke ground on this 280-unit multifamily project consisting of 12 buildings in March 2021 and is expected to begin opening the apartment buildings one at a time every few weeks, according to Greystar Properties. The 28-acre site is located at 451 FM 306. More than half of the apartments will be one- bedroom, one-bathroom homes. Space: 28 acres Timeline: March 2021-23

THE VILLAGE AT BASEL Four duplex-style condominium residences feature 9- to 10-foot ceilings and come in two-bedroom, two-bathroom and three-bedroom, two-bathroom congurations ranging from 1,000-1,200 square feet each. The development, located near the corner of Basel Street and Grant Avenue, is built on raised pillars or stilts due to its ood plain proximity, and its expected completion is within the next month. Space: 1,000-1,200 square feet Timeline: completion set for fall 2022

35

306

C

L U

N

N

N

FARM HAUS The housing development Farm Haus began construction on South Kowald lane in March 2021 and is anticipated to be completed near the end of 2023. The two-story designer homes have a modern farmhouse style and are being sold for around $450,000. Sixty homes are being constructed with oor plans ranging from three bedrooms with two-and-a- half baths to four bedrooms with three-and-a-half baths. The housing development will reside in Solms Landing, a 98-acre mixed-use development that will include apartments, retail, entertainment and dining. Space: 60 single-family homes Timeline: March 2021-December 2023

1101

COOL BREEZE

35

N

SIERRA MARTINCOMMUNITY IMPACT