BY JAMIE MOORE
Academic excellence
Discovery and research
New projects
Several projects include expansions in Round Rock and other satellite locations, plus online programs accessible statewide. On the San Marcos campus, plans feature a new music building, a gallery linked to the performing arts center, renovations of Supple Science, Encino Hall, Jackson Hall, a campus hotel, theater center restoration and adaptable space behind Lantana Hall.
One of Texas State’s goals is to make research a top priority, according to plan documents. To support this, the university plans to complete a Science, Technology, Engineering and Math, or STEM, neighborhood and expand space through new and renovated facilities. The area will feature an Integrated Science and Discovery Building, parking garage, quad and a pedestrian bridge. Renovations will include Thornton House and the Science Greenhouse.
The following projects are part of the 2025-2035 Campus Master Plan.
Hotel: planning and approval underway Academic Center: planning and approval underway STEM Building: 2024-2027 Hilltop Housing Phase 2: pending design approval Castro Residence Hall: 2023-mid-2025 South Endzone Complex: completed May 2025
Baseball/Softball Club House: 2025-late 2028
Lindsey Street Garage: mid-2025-mid-2027
Indoor Practice Facility: 2028-late 2029
Integrated Science & Discovery Building: 2028-late 2031
Spring Lake Dam Replacement: 2028-late 2031
A new music building is planned to support the growing School of Music.
Construction of a new STEM neighborhood to promote research initiatives is planned.
Charles Austin Garage: 2030-late 2031 Mitte Building Expansion: 2029-mid-2032 Harris Dining Hall Expansion: mid-2030-mid-2032
Music Building: 2033-late 2036
Community and stewardship
Future Exhibition or Performance: 2033-late 2035 Blanco Addition: 2035-late 2036
Spring Lake
Texas State aims to improve mobility on campus, while preserving Spring Lake and Sewell Park. Texas State’s “vision” for Spring Lake includes a new academic center, welcome center, event pavilion, heritage walk, blu trail, discovery peninsula and recreation corner. Notably, Texas State plans to restructure Aquarena Gateway and add a trail under.
Live Oak Garage: 2035-late 2036
Arts/Academic Building: 2036-late 2038 Student Health Center Expansion: proposed variable timeline
Sewell Park
Signature Bell Tower: proposed variable timeline
The master plan has a new “vision” for both Sewell Park and Spring Lake.