Transportation
BY JESSICA SHORTEN
3 Louetta Road asphalt rehabilitation Project: This project will allow for the asphalt rehabilitation of Louetta Road from Champion Forest Drive to Holzwarth Road. Update: This project is in the design stage, with a potential timeline available soon.
Update: Work is underway to make asphalt improvements along Hargrave Road. • Cost: $1.4 million • Timeline: March 2026 • Funding source: Harris County Precinct 3 6 Stuebner Airline bridge repairs Project: This project will repair the bridge portion of Stuebner Airline Road over Cypress Creek near Cypresswood Drive. Update: Work has begun on the bridge repair along • Funding source: Harris County Precinct 3 7 Old Town Spring pavement repair Project: The Old Town Spring road project is part of what Precinct 3 ocials call an asphalt package, which includes repairing, milling and resurfacing existing roads. New roadway signage and pavement markings will also be installed. Stuebner Airline. • Cost: $900,000 • Timeline: December 2025 Update: Main Street and Gentry Street are set to be completed by the end of the year according to Precinct 3 ocials. • Cost: $4.2 million • Timeline: December 2025 • Funding source: Harris County Precinct 3
Upcoming projects
Ongoing projects
HUFSMITH RD.
W. RAYFORD RD.
1
1 Gosling Road at West Rayford trac signal
2C
2A
2B
Project: This project will modify the existing signal with a new mast-arm trac signal to improve trac ow and safety along Gosling Road. The Harris County Precinct 3 Commissioner’s Oce is overseeing the design work. Update: Design work is underway for a potential light at the intersection of Gosling Road and West Rayford Road. • Cost: TBD • Timeline: Early 2027 • Funding sources: Harris County Precinct 3, Texas Department of Transportation 2 Hufsmith Road intersection improvements Project: This will make improvements to the intersections of A Hufsmith Road at Kuykendahl Road, B Stuebner Airline Road, and C FM 2978. Update: This project is now in the design phase for future planning and construction according to Harris County Precinct 3.
45
SPRING STUEBNER LP.
SAWDUST RD.
2978
STUEBNER AIRLINE RD.
• Cost: $539,909 • Timeline: TBD • Funding source: Harris County Precinct 3
BORDER ST.
8
7
SPRING STUEBNER RD.
Ongoing projects
LEITNER LN.
HOLZWARTH RD.
2920
SPRING CYPRESS RD.
99 TOLL
SPRING CYPRESS RD.
4 Spring Cypress Road and Louetta Road asphalt rehabilitation Project: This project will rehabilitate asphalt on Spring Cypress Road, from A west of Stuebner Airline to east of T.C. Jester Blvd. and B Louetta Road, from Old Louetta to east of Champion Forest Drive. Update: Work has begun along Spring Cypress Road to replace asphalt as part of an asphalt rehabilitation eort. • Cost: $6.5 million • Timeline: March 2026 • Funding source: Harris County Precinct 3 5 Hargrave Road asphalt rehabilitation Project: This project will allow for asphalt rehabilitation on Hargrave Road from Hwy. 249 to Falba Road.
4A
CYPRESSWOOD DR.
59
3
8 Spring Stuebner Road expansion Project: Expand Spring Stuebner Road from two to four lanes from west of Leitner Lane to the Grand Parkway. Existing drainage and trac signals will also be improved and added as needed. Update: Precinct 3 ocials said construction on this project is expected to take roughly one year to complete. • Cost: $8.1 million • Timeline: Second quarter 2026 • Funding source: Harris County Precinct 3
E
OLD LOUETTA RD.
6
4B
FALBARD.
5
CHAMPION FOREST DR.
• Cost: $36,645 • Timeline: TBD • Funding source: Harris County Precinct 3
HARGRAVE RD.
249
249
2920
MAP NOT TO SCALE N
NORTH LOUETTA 1614 Louetta (281) 350-1198 KUYKENDAHL 13313 Kuykendahl (281) 873-5220
SPRING STUEBNER 6603 Spring Stuebner Rd (281) 288-0239
LOUETTA 7314 Louetta (281) 370-1986
WILLOWBROOK 6927 FM 1960 W (281) 580-1734
Powered by FlippingBook