BY SAMANTHA DOUTY

4 Warren Parkway improvements Project: Warren Parkway will be improved from Legacy Drive to Internet Boulevard. Update: Project details are not finalized and the project is in the design phase. • Timeline: early 2027-mid 2028 • Cost: $4.2 million • Funding source: city of Frisco 5 Legacy Drive upgrades Project: Legacy Drive will be updated from Main Street to Panther Creek Parkway. Update: The project is in the design phase and details are not yet available. • Timeline: mid 2027-mid 2029 • Cost: $23 million • Funding sources: city of Frisco, external sources 6 Hillcrest Road construction Project: Hillcrest Road will be constructed to a four-lane roadway from Eldorado Parkway to Main Street. Update: The project is in the planning phase and is part of a developer agreement. • Timeline: early 2028-mid 2029 • Cost: TBD • Funding source: TBD

• Timeline: late 2024-late 2026 • Cost: $11.03 million • Funding source: city of Frisco 10 Eldorado Parkway traffic signal installation Project: A traffic signal is being installed at the intersection of Eldorado Parkway and Research Road. Update: The project is under construction and is expected to be nearing completion. • Timeline: late 2024-mid 2025 • Cost: $250,000 • Funding source: city of Frisco 11 King Road construction Project: King Road is being widened to a three- and four-lane roadway. The project spans from Rose Lane to Witt Road. Update: The project is under construction and is expected to be completed next year. • Timeline: late 2025-mid 2027 • Cost: $12.5 million • Funding sources: city of Frisco, external funding

Ongoing projects

7 PGA Parkway construction Project: PGA Parkway will be constructed from Preston Road to Coit Road. The project will construct a six-lane divided roadway. Update: The project is nearing completion. • Timeline: late 2024-mid 2026 • Cost: $31.1 million • Funding sources: city of Frisco, external funding 8 Teel Parkway widening Project: Teel Parkway will be widened from a two-lane roadway to a four-lane roadway. The project spans from Stafford Middle School to Olive Branch Road. Update: The project is under construction and is expected to be completed early next year. • Timeline: mid 2025-early 2027 • Cost: $9.36 million • Funding sources: city of Frisco, external funding 9 Mahard Parkway construction Project: The project will construct a six-lane roadway from PGA Parkway to US 380. The project is part of the larger Firefly Park development. Update: The project is under construction and is expected to wrap later this year.

Powered by