Transportation

BY JACQUELYN BURRER

Upcoming projects

SRT TOLL

1 Intersection improvements Project: Plano officials are working to make improvements to city intersections, including adding more turn lanes and upgrading traffic signals. Update: Plano City Council approved a $2.594 million contract at its Aug. 25 meeting for intersection improvements at A Legacy Drive and SH 121, B SH 121 and JP Morgan Driveway, C Corporate Drive and Legacy Drive, and D Corporate Drive and Tennyson Parkway. • Timeline: September 2025-June 2026 • Cost: $2.594 million Project: The street is set to undergo removal and replacement of pavement, sidewalks and water lines along 15th Street from Municipal Avenue to Jupiter Road. Update: Design of the project is currently underway, and construction is expected to begin in summer 2025 after Plano City Council approved a $6.939 million construction contract at its Aug. 25 meeting. • Timeline: August 2025-May 2027 • Cost: $6.939 million • Funding source: city of Plano • Funding source: city of Plano 2 15th Street paving and waterline reconstruction

9

MCDERMOTT DR.

INDEPENDENCE PKWY.

1A 1B

121

75

HEDGCOXE RD.

1C

7

8

CORPORATE DR.

LEGACY DR.

1D

4

TENNYSON PKWY.

SPRING CREEK PKWY.

5

Plano

10

PARKER RD.

DNT TOLL

3

6

PARK BLVD.

MUNICIPAL AVE.

W. 15TH ST.

PGBT TOLL

2

PLANO PKWY.

MAP NOT TO SCALE N

7 Custer Road asphalt overlay Project: Concrete replacement and arterial overlays Update: Construction is expected to begin Aug. 27 for concrete repairs on Custer Road from Spring Creek Parkway to Hedgcoxe Road. • Timeline: August 2025-October 2026 • Cost: $1.63 million • Funding source: city of Plano

Ongoing projects

Ongoing projects

3 Park Boulevard asphalt overlay Project: Crews are undergoing the arterial overlay process, which consists of replacing sections of concrete before sealing with a protective layer. The process aims to expand the road’s lifespan. Update: Road paving from Parker Road to Hedgcoxe Road is scheduled to be complete in September. • Timeline: April 2024-September 2025 • Cost: $2.085 million • Funding source: city of Plano 4 Alma Drive asphalt overlay Project: Concrete replacement and arterial overlays Update: Road paving from Parker Road to Hedgecoxe Road is scheduled to be complete in September. • Timeline: May 2025-September 2025 • Cost: $6.60 million • Funding source: city of Plano 5 Midway Road asphalt overlay Project: Concrete replacement and arterial overlays Update: Road paving from Spring Creek Parkway to Park Boulevard is expected to be complete in September. • Timeline: Fall 2024-September 2025 • Cost: $6.60 million • Funding source: city of Plano 6 Coit Road asphalt overlay Project: Concrete replacement and arterial overlays. Update: Arterial concrete repairs began Aug. 13 along Coit Road from SH 190 to Parker Road. • Timeline: July 2025-July 2026 • Cost: $1.611 million • Funding source: city of Plano

Completed projects

8 Legacy Drive asphalt overlay Project: Concrete replacement and arterial overlays Update: Arterial concrete repairs along Legacy Drive from Coit Road to Custer Road are ongoing and are expected to wrap up Aug. 29. • Timeline: March 2024-August 2025 • Cost: $3.926 million • Funding source: city of Plano 9 Independence Parkway asphalt overlay Project: Concrete replacement and arterial overlays Update: Overlays are from Spring Creek Parkway to SH 121 wrapped up in August, and contractors finished permanent pavement markings. • Timeline: May 2025-August 2025 • Cost: $6.60 million • Funding source: city of Plano

10 Park Boulevard water rehabilitation project Project: The two-phase project, stretching from Preston Road to Plano’s east city limits combined, is working to replace the waterlines running under Park Boulevard. Update: Construction is underway, and both phases are expected to wrap up in September. • Timeline: September 2024-September 2025 • Cost: $9.58 million • Funding source: city of Plano