Transportation
BY GRACIE WARHURST
195
35
Upcoming projects
1 Williams Drive Project: Construct medians with turn lanes on Williams Drive from I-35 to Serenada Drive, including a shared- use path on the north side of Williams Drive, a new waterline, and street lighting from DB Wood Road to Jim Hogg Road and Serenada Drive to I-35 Update: The project’s design is complete, and ocials anticipate it to go out to bid in March. • Timeline: 2023-27 • Cost: $18.6 million • Funding sources: city of Georgetown, trafic impact fees, federal grants, tax increment inancing 2 SE Inner Loop Project: Widen 2.91 miles of SE Inner Loop to a four-lane, divided road from Hwy. 29 to FM 1460, and add a shared- use path for pedestrians and bicycles on one side Update: The city is in the process of acquiring the right of way needed for the project. Design is complete and ocials anticipate it to go out to bid in July. • Timeline: 2022-28 • Cost: $70.6 million • Funding sources: city of Georgetown, Georgetown Transportation Enhancement Corporation 3 Hwy. 29 West Project: Construct additional travel lanes, lengthen turn lanes and improve trac signals on Hwy. 29 from Wolf Ranch Parkway to I-35 as well as add shared-use paths Update: TxDOT is expected to begin construction in July. • Timeline: 2023-27 • Cost: $12.31 million • Funding source: Georgetown Transportation Enhancement Corporation 4 Austin Avenue pedestrian bridges Project: Construct two pedestrian and bicycle bridges crossing the San Gabriel River, east of the existing Austin Avenue vehicular bridges Update: The revised design is tentatively scheduled to complete in July 2027. • Timeline: 2023-TBD • Cost: $21 million • Funding sources: city of Georgetown, developer fees 5 Shell Road Project: Widen Shell Road from Williams Drive to Sycamore Street to four lanes with a raised median, shared-use path, and left- and right-turn lanes Update: As of February, crews were working on utility installation for waterlines and storm water.
DEL WEBB BLVD.
JIM HOGG RD.
SERENADA DR.
SYCAMORE ST.
5
SHELL RD.
NORTHWEST BLVD.
LAKE GEORGETOWN
130 TOLL
1
35
OAK RIDGE RD.
RIVERY BLVD.
WOLF RANCH PKWY.
9
UNIVERSITY PARK DR.
3
DAVIDSON RANCH DR.
2
SOUTHWESTERN BLVD. U
29
1 TO
CHURCHILL FARMS DR.
7
1460
A
8
SAM HOUSTON AVE.
35
N. AUSTIN AVE.
4 6
S. ROCK ST.
W. 2NDST.
1460
MAP NOT TO SCALE N
MAP NOT TO SCALE N
• Timeline: 2024-26 • Cost: $12.78 million
roadway with a continuous center left-turn lane and a 10-foot-wide shared-use path along one side from SE Inner Loop to Sam Houston Avenue Update: Substantial construction is expected by the end of September • Timeline: 2022-26 • Cost: $12 million • Funding source: city of Georgetown 9 DB Wood Road Phase 1 Project: Add four 12-foot-wide lanes, a center turn lane and a 10-foot shared-use path from Hwy. 29 to Oak Ridge Road Update: All roads will be open for trac in May, with substantial completion planned for July
1431 Boulevard to two lanes with a center turn lane and other improvements from University Park to SE Inner Loop Update: Crews have installed the curb as well as about 80% of the new sidewalk along Southwestern Boulevard from Davidson Ranch to SE Inner Loop as of February. • Funding source: city of Georgetown 7 Southwestern Boulevard Project: Reconstruct and expand Southwestern • Timeline: 2020-26 • Cost: $6.58 million • Funding source: city of Georgetown, Williamson County 8 Rockride Lane Project: Upgrade Rockride Lane to a two-lane collector
• Timeline: 2022-27 • Cost: $18.17 million • Funding source: city of Georgetown
35
Ongoing projects
1431 Project: Rehabilitate the Austin Avenue bridges to include new safety-rated rails, required maintenance and a new bridge deck Update: Construction is ongoing, and is expected to wrap up in the spring. 6 Austin Avenue vehicular bridge rehabilitation
• Timeline: 2023-26 • Cost: $29.6 million • Funding source: city of Georgetown
24
COMMUNITYIMPACT.COM
Powered by FlippingBook