Transportation
BY COLBY FARR
City ocials anticipate two projects along Leg- acy Drive in Plano will nish by the end of 2025. What you need to know A $4.7 million project to repair Legacy Drive between Coit Road and Custer Road is expected to nish in October, Senior Engineer Samson Bekele said. Repairs between Coit Road and Indepen- dence Parkway are nished, while repairs between Independence Parkway and Quarry Chase Trail are almost done. Intersection improvements along Legacy Drive are underway at K Avenue, Independence Parkway and Custer Road are expected to be nished by May 2025, City Engineer Josh McNeil said. Legacy Drive improvements near completion
Work on multiple Legacy Drive construction projects is set to nish soon.
MICHAEL CROUCHLEYCOMMUNITY IMPACT
Completed Ongoing
INDEPENDENCE PKWY.
75
Cost: $2.9M
Cost: $2.9M
LEGACYDR.
Cost: $4.7M
Cost: $2.9M
Cost: $4.7M
N
19