Transportation
BY JARRETT WHITENER
Ongoing projects
GREEN VALLEY RD.
35
3009
1103
4
2
WAGON WHEEL WAY
2252
Cibolo
A
N
GREEN VALLEY RD.
78
3B
1518
1 FM 1518 Project: A About 5.6 miles of FM 1518 will be reconstructed by widening the existing roadway. Two 11-foot lanes will be constructed in each direction, alongside a raised center median, and shared-use paths on each side of the roadway. Update: TxDOT plans to complete stormwater upgrades and a shared-use path addition on the east side of FM 1518, south of Lisa Meadows; intersection improvements at B Lower Seguin Road, C Ray Corbett Drive and D Schaefer Road; Schertz water and sewer line upgrades. • Timeline: Spring 2024-Spring 2028 • Cost: $72.78 million • Funding sources: TxDOT, city of Schertz
W. SCHAEFER RD.
Universal City
CIBOLO VALLEY DR.
SILVER WING
RAY CORBETT DR.
3A
1D
1C
1604
1B
FIREBIRD RUN
Schertz
1A
1518
10
N
MAP NOT TO SCALE
• Timeline: September 2025-Spring 2026 • Cost: $3.1 million • Funding source: City of Cibolo iscal year 2025 Certiicate of Obligation Bonds 4 FM 2252 Project: Work on this project will consist of the expansion of the roadway from two lanes to four lanes, with a raised median or continuous left turn lane, bike lanes and sidewalks. Update: Alternating lane closures will continue being implemented along the roadway, causing regular delays. During construction, motorists are encouraged to use caution or an alternative route. • Timeline: 2024-2028 • Cost: $48.5 million • Funding source: TxDOT
work are underway concurrently with other roadwork. • Timeline: November 2022-2030 • Cost: $39.29 million • Funding sources: TxDOT, city of Cibolo, city of Schertz 3 Cibolo FY25 Street Rehabilitation Package II Project: The reconstruction of A Firebird Run, Silver Wing and B Town Creek Road. This is the second set of roads funded for reconstruction under the 2025 general obligation bonds. The rst phase included construction on Deer Creek Boulevard and Green Valley Road. Update: Work on Silver Wing is substantially completed, and work on Town Creek Road is expected to wrap up in February. The construction on Firebird Run began on Jan. 8 and is expected to be completed in the Spring.
Ongoing projects
2 FM 1103 Project: The Texas Department of Transportation, or TxDOT, is improving FM 1103 from I-35 to Rodeo Way in Comal and Guadalupe counties to increase mobility, enhance safety and reduce congestion. The project will expand the road from two to four lanes and add sidewalks and bike lanes in each direction. Update: A lane on FM 1103 between Green Valley Road and Wagon Wheel Way closed from Jan. 19-23 as crews build a future detour for Phase 3 of the project. The contractor removed pavement markings for detour sections and implemented a trac lane switch. After the switch, crews will begin work in additional areas for the proposed widening. Driveway and drainage