Transportation
BY VANESSA HOLT
Gosling Road. It will also extend lanes from Gosling Road to Research Forest Drive in both directions. Update: Utility coordination and relocation was
Hwy. 242 between FM 1488 and I-45 to widen lanes and restripe the intersections. Update: As of the most recent information released by TxDOT in October, the project, which is being carried out by Posillico Civil Inc., was 68% complete. • Cost: $29.11 million • Timeline: Oct. 23, 2023-fourth quarter 2026 • Funding sources: federal, state funds
45
1488
242
underway in November. • Cost: $25,500 (design)
6
GREENBRIDGE DR.
• Timeline: Construction will begin in early 2026. • Funding source: Montgomery County road bond 3 Woodlands Parkway at Kuykendahl Road turn lane extension Project: The project will add a left-turn lane and extend lane storage from northbound Kuykendahl Road to westbound and eastbound Woodlands Parkway. Update: Utility coordination and relocation began as of a November update, Precinct 3 officials said. • Cost: $88,240 (design) • Timeline: Construction will begin in spring or summer 2026. • Funding source: Montgomery County road bond 4 Grogan’s Mill Village Center signalization Project: A traffic signal will be replaced at the intersection of Grogans Mill Road and the entrance to the Grogan’s Mill Village Center, according to Precinct 3. Update: Engineering design was underway as of Nov. 10. • Cost: $52,500 (design) • Timeline: Construction is slated to begin in summer 2026. • Funding source: Montgomery County road bond
VISION PARK BLVD.
8
2
The Woodlands
Completed projects
RESEARCH FOREST DR.
LAKE WOODLANDS DR.
7 Grogans Mill Road at Research Forest Drive right turn improvements Project: The project will extend a right-turn lane from northbound Grogans Mill Road onto eastbound Research Forest Drive. Update: Construction was completed as of a Nov. 10 update from Montgomery County Precinct 3. • Cost: $50,000 (design), $211,671 (construction) • Timeline: June-August (design), September-October (construction) • Funding source: Montgomery County road bond 8 Research Forest Drive at Greenbridge Drive turn lane extension Project: The project extended and widened the left- turn lane from eastbound Research Forest Drive to northbound Greenbridge Drive. Update: As of a November update, work was completed. • Cost: $10,500 (design), $198,150 (construction) • Timeline: June-August (design), October-November (construction) • Funding source: Montgomery County road bond 9 Lake Woodlands Drive at East Panther Creek Drive turn-lane extension Project: The project will extend the left-turn lane from westbound Lake Woodlands Drive onto southbound East Panther Creek Drive. Update: As of a November update, the project was completed. • Cost: $22,500 (design), $116,057 (construction) • Timeline: June-August (design), September-November (construction) • Funding source: Montgomery County road bond
3
7
9
1
LAKE WOODLANDS
E. PANTHER CREEK DR.
4
BRANCH CROSSING DR.
STERLING RIDGE DR.
GROGANS MILL VILLAGE CENTER
WOODLANDS PKWY.
5
MAP NOT TO SCALE N
Upcoming projects
1 Lake Woodlands Drive at Gosling Road intersection improvements Project: The project will extend turn lanes to improve mobility and safety from eastbound Lake Woodlands Drive onto northbound Gosling Road. It will also extend turn lanes from westbound Lake Woodlands Drive onto southbound Gosling Road. Update: Utility coordination and relocation was underway in November, Precinct 3 officials said. • Cost: $40,000 (design) • Timeline: Construction will begin in early 2026. • Funding source: Montgomery County road bond 2 Research Forest Drive at Gosling Road turn lane extension Project: The project will extend dual left-turn lanes from westbound Research Forest Drive to southbound 99 TOLL
Ongoing projects
5 Woodlands Parkway at Branch Crossing Drive turn lane extensions Project: The left-turn lane will be extended from westbound Woodlands Parkway to southbound Branch Crossing Drive, as well as from Branch Crossing Drive onto eastbound Woodlands Parkway. Update: Construction has started on the Branch Crossing left-turn lane extension. • Cost: $58,000 (design), $310,876 (construction) • Timeline: Work will be completed by the end of the year. • Funding source: Montgomery County road bond 6 Hwy. 242 widening Project: TxDOT is using the existing right of way on
INSURED
112
HOUSE CLEANING S vice • 1 English-speaking maid per job • All supplies included
FREE OVEN CLEANING with Bi-Weekly Service
• 24-hour satisfaction guarantee • No contracts, no hidden fees
TEXT/CALL (281) 630-1216
Limitations apply. See geico.com for more details. GEICO & affiliates. Washington, DC 20076. GEICO Gecko image © 1999-2024. © 2024 GEICO. 21_633312129
LemurCleaning@gmail.com | www.LemurCleaning.com
33
THE WOODLANDS EDITION
Powered by FlippingBook