Prosper - Celina | December 2025

Transportation

BY JACQUELYN BURRER

Update: The project is in the design phase and construction has been delayed to start in summer 2028 to align with the Upper Trinity Regional Water District’s treatment plant expansion. • Timeline: summer 2028-summer 2029 • Cost: $13.45 million • Funding source: town of Prosper 6 Coit Road resurfacing Project: This project includes an asphalt restoration of Coit Road in three segments. The segments are A CR 100 from Preston Road to CR 97, B County Road 90 from CR 92 to CR 98, and C CR 97 from Lynn Stambaugh Parkway to CR134. Update: The project is in the design phase and all the plans are ready for bidding. • Timeline: estimated completion September 2026 • Cost: $3.49 million • Funding source: city of Celina

• Cost: $4.2 million • Funding source: city of Celina 8 US 380 widening

along Frontier Parkway from east of Preston Road to Coit Road. The work is being completed due to the Texas Department of Transportation project to widen Frontier Parkway from Preston Road to Custer Road. Update: Construction is expected to start in January. • Timeline: January 2026-July 2026 • Cost: $1.7 million • Funding source: city of Celina 4 Legacy Drive widening Project: This project will widen several lanes through the Legacy Drive and Prosper Trail intersection. Update: At a Dec. 9 meeting, Prosper Town Council members approved a roadway design, construction and reimbursement agreement with Blue Star Land that adds two southbound lanes on Legacy Drive through the Prosper Trail intersection. Construction costs will be covered by general obligation bonds approved by voters in November, which included $10 million for Legacy Drive improvements from Prosper Trail to Parvin Road. • Timeline: summer 2026-TBD • Cost: $1.23 million

Upcoming projects

134

455

6C

1 Marilee Road reconstruction Project: The project spans Marilee Road from Preston Road to Dallas Parkway. The project is shared with the city of Gunter, Grayson County, Collin County, city of Celina and the adjacent subdivision developers. Update: The project is in the design phase and is nalizing additional right of way components. • Timeline: TBD • Cost: $8.7 million • Funding source: city of Celina, other entities 2 US 380 waterline reconstruction Project: The project stretches along US 380 from Coit Road to Custer Road. Update: At a Nov. 25 meeting, Prosper Town Council approved a $1 million contract with Freese and Nichols Inc. to design a project relocating water and wastewater lines along US 380 between Coit and Custer roads. • Timeline: TBD • Cost: $1 million • Funding source: town of Prosper 3 Frontier Parkway waterline reconstruction Project: This project will replace existing water lines

MARILEE RD.

97

Project: TxDOT is widening US 380 from the Collin County and Denton County line to Loop 288 from four lanes to six lanes. Update: Trac switches are ongoing. • Timeline: January 2022-March 2026 • Cost: $175.66 million • Funding source: TxDOT, other entities 9 First Street construction Project: The project will create four lanes from Stuber Elementary to North Dallas Parkway.

100

1

LYNN STAMBAUGH PKWY.

6A

97

455

90

98

SUNSET BLVD.

6B

92

428

7

1385

289

6

428

Update: The project is nearing completion. • Timeline: spring 2023-December 2025 • Cost: $30.89 million • Funding source: town of Prosper 10 Coit Road construction

3

FRONTIER PKWY.

Ongoing projects

PARVIN RD.

5

4

• Funding source: town of Prosper 5 Prosper Trail construction

Project: The rst phase of the project, which spans Coit Road from First Street to Prosper Trail, will design and construct four lanes of an ultimate six-lane roadway. Update: The project is expected to wrap next summer. • Timeline: summer 2025-summer 2026 • Cost: $19.85 million • Funding source: town of Prosper

7 Sunset Boulevard asphalt improvements Project: The asphalt pavement along Sunset Boulevard from Preston Road to Coit Road will be replaced. Update: The project is under construction and is at 80% completion. • Timeline: estimated completion January 2026

Prosper

E. PROSPER TRL.

10

9

COUNTY RD.

FISHTRAP RD.

FIRST ST.

Project: Prosper Trail will be reconstructed from Coit Road to Custer Road and the bridge will be replaced at the Wilson Creek crossing. It will be a four-lane divided roadway.

8

2

LOVERS LN.

380

380

MAP NOT TO SCALE N

423

PROSPER 950 S Preston Rd (469) 535-5539 LITTLE ELM 27100 Hwy 380 (972) 347-9630