Transportation
BY JENNA STEPHENSON
preparation for an asphalt overlay. Update: Arterial concrete repairs on Custer Road from Hedgcoxe Road to Spring Creek Parkway are underway. • Timeline: August 2025-October 2026 • Cost: $1.63 million • Funding source: city of Plano 4 Coit Road asphalt overlay Project: The road is receiving arterial concrete repairs in preparation for an asphalt overlay. Update: Arterial concrete repairs on Coit Road from President George Bush Turnpike to Parker Road are underway. • Timeline: July 2025-July 2026 • Cost: $1.61 million • Funding source: city of Plano 5 Plano Parkway sewer improvements Project: Plano is working to make sewer improvements along Plano Parkway to increase sewer capacity for current and future development in the area. Update: Several lanes along Plano Parkway will see
6 Legacy Drive intersection improvements Project: Crews are working to improve intersections in west Plano, including Corporate Drive and Legacy Drive. Update: Several lanes along Legacy Drive will see closures for ongoing construction. • Timeline: September 2025-June 2026 • Cost: $2.59 million • Funding source: city of Plano
Ongoing projects
DNT TOLL
Upcoming project
INDEPENDENCE PKWY.
75
1 Custer Road Project: The North Texas Municipal Water District is currently working to replace an aging pipeline along Custer Road. Update: A total of 4,900 feet of the 9,100-foot pipeline has been installed, according to a city news release. Permanent paving at West 15th Street and Pitman Drive will be scheduled pending water testing. • Timeline: February 2025-October 2026 • Cost: $18 million • Funding source: North Texas Municipal Water District 2 15th Street paving and waterline reconstruction Project: The project involves the removal and replacement of pavement, sidewalks and water lines along 15th Street from Municipal Avenue to Jupiter Road. Update: Traffic lane widths are reduced to allow for utility installation from Municipal Avenue to P Avenue. • Timeline: August 2025-March 2027 • Cost: $6.94 million • Funding source: city of Plano 3 Custer Road asphalt overlay Project: The road is receiving arterial concrete repairs in
MCDERMOTT RD.
CORPORATE DR.
HEDGCOXE RD.
BETHANY DR.
6
3
SRT TOLL
Upcoming projects
LEGACY DR.
7 Los Rios Boulevard at Plano East High School paving improvements Project: This project includes modifications to the existing median openings in both the northbound and southbound lanes along Los Rios at Plano East Senior High School. Update: City Council approved a contract with Garret Shields Infrastructure, LLC at its April 13 meeting. • Timeline: April 2026-TBD • Cost: $293,900 • Funding source: city of Plano
SPRING CREEK PKWY.
WINDHAVEN PKWY.
LOS RIOS BLVD.
8 G Avenue paving and water improvements Project: Crews will replace a waterline and pavement on G Avenue between 14th and 15th Street. Improvements will also add on-street parking, enhance sidewalks and update traffic signals. Update: Construction is scheduled to start July 30
PARKER RD.
7
4
PARK BLVD.
G AVE.
MUNICIPAL AVE.
2
PITMAN DR.
15TH ST.
PLANO PKWY.
8
5
closures as construction continues. • Timeline: July 2025-spring 2027 • Cost: $16.1 million • Funding source: city of Plano
PLANO PKWY.
and wrap up in mid-December. • Timeline: July–December 2026 • Cost: $374,800 • Funding source: city of Plano
PGBT TOLL
LOS RIOS BLVD.
1
MAP NOT TO SCALE N